Converted · interior conversion · Visitacion Valley
1 Ankeny St
In progress+1 unit on this lot · now 21 permit
Convert existing bedroom, workroom and laundry into a new ADU and add new kitchen.
filed Feb 2026issued May 2026 · permit wait 3 months6 months since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$50,000
declared on the ADU permit
Permit wait
3 months
filed → issued
Build time
in progress
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Convert existing bedroom, workroom and laundry into a new ADU and add new kitchen. 202506168790 · Culligan Construction | filed Feb 2026 · issued May 2026 | $50k | city record |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 6168, lot 002
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.