Converted · garage conversion · Inner Sunset
1044 Judah St
Completed Aug 2024+4 units on this lot · now 1011 permits
At existing parking garages at first floor, replace parking with four new accessory dwelling units (adus) per ordinance no. 162-16. Separate building permit for related seismic soft-story retrofit (ssr).
filed Jun 2020issued Mar 2022 · permit wait 1 year 10 monthscompleted Aug 2024 · built in 2 years 5 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$553,111 for 4 ADUs
one permit, 4 units; not a per-unit price
Permit wait
1 year 10 months
filed → issued
Build time
2 years 5 months
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | At existing parking garages at first floor, replace parking with four new accessory dwelling units (adus) per ordinance no. 162-16. Separate building permit for related seismic soft-story retrofit (ssr). 202006118444 · Macrobuild Corporation | filed Jun 2020 · issued Mar 2022 · done Aug 2024 | $480k | city record |
| Sprinklers | Install new fire sprinkler system per nfpa13 througout the ground floor only in alarm 2" underground fire service total 44 heads ref pa 2020-0611-8446. 202302131865 · Magnum Construction Group INC | filed Feb 2023 · issued Feb 2023 · done Jul 2024 | $39k | city record |
| Related permit | Replace existing fire alarm system to comply with sffc 1103. 7. 6. 1 replace 9e) facp with new facu; install power supply, smoke detectors, pull stations, aes radio, monitoring modules and horn strobes; install lf sounders in all units potential sleeping areas to comply with sffd 1103. 7. 6. 1. 202401033359 · San Francisco Fire Protection | filed Jan 2024 · issued Jan 2024 · done Jun 2024 | $34k | city record |
| Electrical | Unit #10: ADU units, electrical wiring panel box and meter, kitchen appliances and bathroom. E202204149605 | Apr 14, 2022 → Jul 2, 2024 | — | |
| Electrical | Unit #9: ADU units, electrical wiring panel box and meter, kitchen appliances and bathroom. E202204149604 | Apr 14, 2022 → Jul 2, 2024 | — | |
| Electrical | Unit #7: ADU units, electrical wiring panel box and meter, kitchen appliances and bathroom. E202204149598 | Apr 14, 2022 → Jul 2, 2024 | — | |
| Electrical | Unit #8: ADU units, electrical wiring panel box and meter, kitchen appliances and bathroom. E202204149603 | Apr 14, 2022 → Jul 2, 2024 | — | |
| Electrical | Fire alarm system upgrade to add low frequency sounders in existing units upstairs and ground floor additional units. EW202301268625 | Jan 26, 2023 → Jun 13, 2024 | — | |
| Plumbing | Units #7, 8, 9, 10: ADU units, sewer lines, water lines and gas lines and meters. PP20220414293 | Apr 14, 2022 → Sep 5, 2023 | — | |
| Plumbing | Relocation of gas meters. Apt # 1, 2, 3, 4, 5, 6 and house meter. Outdoor laundry, replace water heater. PP20230825640 | Aug 25, 2023 → Sep 5, 2023 | — | |
| Plumbing | Unit #7, 8, 9, 10: renewal for pm20220414294 for final inspection. PM20240701642 | Jul 1, 2024 → Jul 25, 2024 | — |
These permits also cite 202006118446, which the city filed before our records begin.
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 1770, lot 024
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.