Converted · Russian Hill
1066A Filbert St
In progress+1 unit on this lot · now 43 permits
Rev to bpa 201904016779 to add state ADU unit 1066a and remodel units 1066, 1068, 1070 as follows: relocate and update gathroomsand kitchens. Improve common areas including new garbage area, utility and meter upgrades gas, electrical, upgrade entrance to lower two units1066-1066a to code. Infill existing.
filed Dec 2025issued Aug 2026 · permit wait 8 months3 months since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$1,000,500 + other work
the permit also covers work unrelated to the ADU, so this is not an ADU price
Permit wait
8 months
filed → issued
Build time
in progress
issued → completed
Builder
No contractor listed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Rev to bpa 201904016779 to add state ADU unit 1066a and remodel units 1066, 1068, 1070 as follows: relocate and update gathroomsand kitchens. Improve common areas including new garbage area, utility and meter upgrades gas, electrical, upgrade entrance to lower two units1066-1066a to code. Infill existing. 202511149623 | filed Dec 2025 · issued Aug 2026 | $1.0M | city record |
| Revision | Revision to pa 202511149623 revise roof deck extend deck to west and next to adjacent lightwell. 202608287344 · cites 202511149623 | filed Aug 2026 · issued Aug 2026 | — | city record |
| Electrical | Rewire unit 1066 new sub panel. All outlet, lights living, dinner area, bathroom, bedrooms power for kitchen appliance. S/d, common area light & outlet. Ufer ground wire. 400amp service with 5 meter. EW202609087779 | Sep 8, 2026 | — |
These permits also cite 201904016779, which the city filed before our records begin.
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 0093, lot 016
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.