Converted · garage conversion · Sunset/Parkside
106A Country Club Dr
In progress+1 unit on this lot · now 26 permits
New 660 sq ft ADU on garage level.
filed Jul 2021issued Mar 2022 · permit wait 8 months4 years 8 months since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$119,645
declared on the ADU permit
Permit wait
8 months
filed → issued
Build time
in progress
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | New 660 sq ft ADU on garage level. 202107134267 · Golden Star Construction | filed Jul 2021 · issued Mar 2022 | $120k | city record |
| Revision | Revision to permit 202107134267. ADU entry door provided at rear. Side entry door and landing eliminated. 202212158450 · cites 202107134267 | filed Dec 2022 · issued Dec 2022 | — | city record |
| Electrical | New electrical for ADU: new plugs, lights, switches, 200a subpanel. E202204129568 | Apr 12, 2022 | — | |
| Electrical | Revision to #e202204129568: electrical baseboard heater will be added to living room as well as the bedroom. E202206301103 | Jun 30, 2022 | — | |
| Plumbing | New mechanical work for ADU including 1 kitchen hood, 1 bathroom fan, 1 air conditioner & 3 ducts for ADU. PM20220412265 | Apr 12, 2022 | — | |
| Plumbing | Work category: 1p; sewer later replacement. PW20260202296 | Feb 2, 2026 → Feb 4, 2026 | — |
1 other permit on this lot during the project, not counted
| Other | Reroofing hot works. 202602115713 · Central Roofing Company | filed Feb 2026 · issued Feb 2026 · done Apr 2026 | $20k | city record |
Trade permits show what work was done and when; the city does not record who pulled them.