Converted · garage conversion · Mission

108 Albion St

Completed Jun 2026+2 units on this lot · now 810 permits

(2) ground floor accessory dwelling units per ordinace 162-16. Units to be located in existing garage & storage space. Ref pa#2016/0428/5904 for soft story retrofit. Infill (2) garage doors and add (3) wood windows & (1) entry doors at front facade. No expansion of building envelope.

filed Dec 2020issued May 2023 · permit wait 2 years 5 monthscompleted Jun 2026 · built in 3 years 1 month
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$182,000 for 2 ADUs
one permit, 2 units; not a per-unit price
Permit wait
2 years 5 months
filed → issued
Build time
3 years 1 month
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permit(2) ground floor accessory dwelling units per ordinace 162-16. Units to be located in existing garage & storage space. Ref pa#2016/0428/5904 for soft story retrofit. Infill (2) garage doors and add (3) wood windows & (1) entry doors at front facade. No expansion of building envelope.
202012070397 · 3serg Homebuilder INC
filed Dec 2020 · issued May 2023 · done Jun 2026$150kcity record
SprinklersNew fire spinkler system and underground for 2 ADU at the ground floor per nfpa 13 ref pa # 2020-1207-0397.
202503313352 · cites 202012070397 · Lowy R Fire Protection INC
filed Mar 2025 · issued Mar 2025 · done Nov 2025$27kcity record
SprinklersInstall new sprinkler monitoring system, ref to ADU pa# 202012070397 & sprinkler 202503313352.
202510097142 · cites 202012070397 · Mcmillen Construction INC
filed Oct 2025 · issued Oct 2025 · done Nov 2025$5,000city record
ElectricalInstall light fixtures, switches, outlets.
E202506163203
Jun 16, 2025 → Oct 3, 2025—
ElectricalUpgrade main electrical service to 400 amps, 8 units and 1 house meter.
EW202506257424
Jun 25, 2025 → Sep 30, 2025—
ElectricalUnit b: install light fixtures, switches and outlets. Unit a: ref: e202506163203.
E202508224997
Aug 22, 2025—
Electrical108-118 albion st. Install new sprinkler monitoring system.
E202510106309
Oct 10, 2025 → Oct 29, 2025—
PlumbingWork category: 4pa; new fire sprinkler system and underground service for the 2 new ADU in the building per nfpa 13 and reference to 202503313352.
PW20250523464
May 23, 2025 → Oct 10, 2025—
PlumbingConverting garage to 2 adus, installing 2 furnaces and 2 water heaters.
PM20250616886
Jun 16, 2025 → Oct 3, 2025—
PlumbingInstall sinks, faucets in kitchens and bathrooms in adus, 108a, 108b.
PP20250616884
Jun 16, 2025 → Nov 3, 2025—

These permits also cite 201604285904, which the city filed before our records begin.

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 3568, lot 027
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map