Converted · ground-floor conversion · Mission

1080 Hampshire St

Completed Mar 2026+1 unit on this lot · now 25 permits

Add 1 unit at gr floor zoning rh2, add 29 SF under 2nd floor overhang at rear, remodel 2nd floor unit. Correct deck and stair rear violation 202183612.

filed May 2024issued Feb 2025 · permit wait 9 monthscompleted Mar 2026 · built in 1 year 1 month
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$543,000 + other work
the permit also covers work unrelated to the ADU, so this is not an ADU price
Permit wait
9 months
filed → issued
Build time
1 year 1 month
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitAdd 1 unit at gr floor zoning rh2, add 29 SF under 2nd floor overhang at rear, remodel 2nd floor unit. Correct deck and stair rear violation 202183612.
202207289445 · Above Engineering Corporation
filed May 2024 · issued Feb 2025 · done Mar 2026$543kcity record
Electrical1080-1080a hampshire run new wiring throughout entire housing including new outlets and lights; bath upstairs and downstairs. Install new subpanel for house.
E202504171738
Apr 17, 2025 → Mar 12, 2026—
PlumbingRun new plumbing for 4 bathrooms and 2 kitchen. Underground. Gas heater.
PP20250417714
Apr 17, 2025 → Mar 16, 2026—
PlumbingWork category: 1m; install a new 96% afue in the garage with new duct works in for the garage unit 1080a.
PMW20250909933
Sep 9, 2025 → Mar 12, 2026—
PlumbingWork category: 1m; remove and replace existing gas furnace with a new one.
PMW20250917116
Sep 17, 2025 → Mar 16, 2026—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 4152, lot 017
Why we call it an ADU
Two independent model reviewers agreed the permit creates an ADU: “"add 1 unit at gr fl zoning rh2"; Existing units: 1 → Proposed units: 2; use 1 family dwelling → 2 family dwelling”
Claim this project or house

City record of the ADU permitProperty Information Map