Converted · interior conversion · Mission

1100 Potrero Ave

In progress+5 units on this lot9 permits

The scope of work iunder this permit is the conversion of the existing unoccupied commercial space to an ADU as per government code section 65852. 2. The unit will contain living-dining, kitchen, bath and bedroom.

filed May 2022issued Aug 2022 · permit wait 3 months4 years 2 months since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$74,200 for 5 ADUs
one permit, 5 units; not a per-unit price
Permit wait
3 months
filed → issued
Build time
in progress
issued → completed
Builder
No contractor listed

Permits in this project

PermitWhatWhenDeclared
ADU permitThe scope of work iunder this permit is the conversion of the existing unoccupied commercial space to an ADU as per government code section 65852. 2. The unit will contain living-dining, kitchen, bath and bedroom.
202205174418
filed May 2022 · issued Aug 2022$70kcity record
SprinklersRevise fire sprinkler system 201503161018, add 4 according to 2022 0517 4418 per nfpa 13 2022. Total add 6 pendemt head at ground floor new dwelling unit and change all pendent heads to flat plate type.
202301200496 · cites 202205174418 · Cj Plumbing INC
filed Jan 2023 · issued Jan 2023 · done Mar 2023$4,200city record
RevisionAs-built: relocated 2 low frequency sounders in 1st flr new ADU unit(previously commercial). Ref 202205174418 ADU/201503161018s5 fire alarm.
202302242607 · cites 202205174418 · Crime Watch Security Sys Llc
filed Feb 2023 · issued Feb 2023 · done Mar 2023—city record
ElectricalNew electrical wiring foe ADU, kitchen, one bedroom and bath.
EW202301138352
Jan 13, 2023 → Mar 27, 2023—
PlumbingWork category: 1m; continue work on expired permit pmw20210817987.
PMW20230126266
Jan 26, 2023 → Feb 1, 2023—
PlumbingWork category: 1m; install one (1) mitsubishi ducted heat pump system.
PMW20230126267
Jan 26, 2023 → May 23, 2023—
PlumbingWork category: 4pa; job description: revise fire sprinkler system 201503161018, add 4 according to 2022 0517 4418 per nfpa 13 2022. Total add 6 pendemt head at ground floor new dwelling unit and change all pendent heads to flat plate type.
PW20230129318
Jan 29, 2023 → Feb 2, 2023—
PlumbingWork category: 1p; ref # 20201015548 on ground floor new ADU; install bathroom, kitchen, washer and dryer.
PW20230129319
Jan 29, 2023 → Jun 5, 2023—
PlumbingWork category: 1p; 1 shower pan.
PW20230327750
Mar 27, 2023 → Mar 29, 2023—
1 other permit on this lot during the project, not counted
OtherPer pa #01503161018, add address 2707, 2709 23rd st for apartment building at apn #4211/001.
M1229787
filed Dec 2022 · issued Dec 2022$439city record

These permits also cite 201503161018, which the city filed before our records begin.

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 4211, lot 001
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house