Converted · ground-floor conversion · Excelsior
114 Florentine Ave
In progress+1 unit on this lot · now 22 permits
Raising existing structure, seismic upgrade of foundation & structure, horizontal expansion of each level, deck, creation of ADU within building perimeter per ordinance 95-17. All new interior kitchens, bathrooms, finishes & insulations.
filed Feb 2019issued Sep 2022 · permit wait 3 years 8 months4 years 1 month since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$345,600 + other work
the permit also covers work unrelated to the ADU, so this is not an ADU price
Permit wait
3 years 8 months
filed → issued
Build time
in progress
issued → completed
Builder
No contractor listed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Raising existing structure, seismic upgrade of foundation & structure, horizontal expansion of each level, deck, creation of ADU within building perimeter per ordinance 95-17. All new interior kitchens, bathrooms, finishes & insulations. 201902052139 | filed Feb 2019 · issued Sep 2022 | $346k | city record |
| Electrical | Installed new gfci and conduits for the water heater. EW202404087889 | Apr 8, 2024 | — |