Converted · garage conversion · Castro/Upper Market

114A Noe St

Completed Feb 2024+2 units on this lot · now 810 permits

New ADU per ord# 162-16 in 1st flr: convert existing garage spaces to two ADU. ADU# 1 to have two bedrooms, two full bathrooms, a kitchen, a living/dining area. ADU# 2: 1 bedroom, 1 full bathroom, a kitchen, a living/dining area. Fire sprinkler uner separate permit.

filed May 2019issued Nov 2021 · permit wait 2 years 6 monthscompleted Feb 2024 · built in 2 years 3 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$251,716 for 2 ADUs + other work
the permit also covers work unrelated to the ADU, so this is not an ADU price
Permit wait
2 years 6 months
filed → issued
Build time
2 years 3 months
issued → completed
Builder
No contractor listed

Permits in this project

PermitWhatWhenDeclared
ADU permitNew ADU per ord# 162-16 in 1st flr: convert existing garage spaces to two ADU. ADU# 1 to have two bedrooms, two full bathrooms, a kitchen, a living/dining area. ADU# 2: 1 bedroom, 1 full bathroom, a kitchen, a living/dining area. Fire sprinkler uner separate permit.
201905019443
filed May 2019 · issued Nov 2021 · done Feb 2024$180kcity record
RevisionRev to pa201905019443 on gt/f au unit per plan. Structural revision only. Replace existing finished floor concret slab at ADU unit to new concrete slab on grade with vapor barrier ssd for details. No change in ceiling height. No underpinning/excavation to be done.
202203180315
filed Mar 2022 · issued Apr 2022 · done Feb 2024$20kcity record
SprinklersInstalling fire sprinklers to accomodate new floor plans ti. Installing 22 new heads ref# pa201905019443 & pa#202203180315.
202206106076 · Freedom Fire Protection INC
filed Jun 2022 · issued Aug 2022 · done Dec 2023$8,740city record
Related permitRef pa# 202206106076, change out 1" meter to 2" combo meter.
202301120110 · Freedom Fire Protection INC
filed Jan 2023 · issued Jan 2023 · done Dec 2023$6,500city record
Related permitFire alarm upgrade.
202307273113 · Luminous Fire Alarm
filed Jul 2023 · issued Dec 2023 · done Dec 2023$36kcity record
ElectricalElectrical work for unit 114 remodel.
E202209072278
Sep 7, 2022 → Dec 28, 2023—
ElectricalElectrical work for unit 124 remodel.
E202209072279
Sep 7, 2022 → Dec 14, 2023—
ElectricalFire alarm upgrade.
E202307278368
Jul 27, 2023 → Dec 28, 2023—
ElectricalUpgrade service electric meter panels from 200 amp to 400 amp, pg&e is been approved and ready to be scheduled,.
EW202309133806
Sep 13, 2023 → Dec 28, 2023—
PlumbingWork category: 2pa; final inspection for 114 a & 114 b noe street, san fransisco ca 94114. Took out new permit instead of renewing expired permit. Final inspection.
PW20231127885
Nov 27, 2023 → Dec 21, 2023—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 3540, lot 003
Why we call it an ADU
SF DBI flagged the permit as an ADU.