Converted · ground-floor conversion · Mission

1157 Valencia St

Completed Dec 2023+1 unit on this lot · now 106 permits

The work involves construction of new ADU (accessory dwelling unit) on the ground floor of an existing apartment structure building with open space.

filed Nov 2020issued Jun 2022 · permit wait 1 year 7 monthscompleted Dec 2023 · built in 1 year 6 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$213,550
declared across 2 permits: the ADU permit plus its sub-permits
Permit wait
1 year 7 months
filed → issued
Build time
1 year 6 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitThe work involves construction of new ADU (accessory dwelling unit) on the ground floor of an existing apartment structure building with open space.
202011209463 · Pineda Construction INC
filed Nov 2020 · issued Jun 2022 · done Dec 2023$190kcity record
Related permitVoluntary system replacement and new lf horns to meet sffc 2022 sec 1103. 7. 6. 1.
202304065205 · C & E Electric & Fire Alarm Services
filed Apr 2023 · issued Nov 2023 · done Dec 2023$24kcity record
ElectricalRewire new ADU and kitchen.
E20220622883
Jun 22, 2022 → Apr 30, 2024—
ElectricalNew fire alarm panel, wireless communicator, smoke, pull, sounders inside unit, horn/strobes.
EW202311105099
Nov 10, 2023 → Dec 19, 2023—
PlumbingTo renew expired per for final inspection. Pp20220622545.
PP20231017560
Oct 17, 2023 → Oct 23, 2023—
PlumbingInstall new mini split in new unit associated with bpa 202011209463.
PM20231026738
Oct 26, 2023 → Nov 30, 2023—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot