Converted · ground-floor conversion · Outer Mission

1161A Cayuga Ave

Completed Mar 2024+1 unit on this lot · now 24 permits

Convert ground floor into ADU, two bedroom, one bath and kitchen space at 576 sq ft per state ADU program.

filed Aug 2022issued Mar 2023 · permit wait 7 monthscompleted Mar 2024 · built in 1 year
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$45,000
declared on the ADU permit
Permit wait
7 months
filed → issued
Build time
1 year
issued → completed
Builder
No contractor listed

Permits in this project

PermitWhatWhenDeclared
ADU permitConvert ground floor into ADU, two bedroom, one bath and kitchen space at 576 sq ft per state ADU program.
202208241212
filed Aug 2022 · issued Mar 2023 · done Mar 2024$45kcity record
RevisionRevision to pa# 202208241212. Alter ADU entrance. Alter half bath in garage.
202307182416 · cites 202208241212
filed Jul 2023 · issued Jul 2023 · done Mar 2024—city record
ElectricalUpgrade 200amp overhead service and electrical lighting/outlet and remodel ADU.
EW202305291448
May 29, 2023 → Jan 18, 2024—
Plumbing2 toilets, 3 sinks, 1 shower, 1 wash machine, 1 dryer.
PP20230522057
May 22, 2023 → Oct 13, 2023—
1 other permit on this lot during the project, not counted
OtherRemove and replace existing post on 1st flr due to damage. No changes to architectural.
202305238415
filed May 2023 · issued May 2023 · done Feb 2024$5,000city record

Trade permits show what work was done and when; the city does not record who pulled them.