Converted · ground-floor conversion · Outer Mission
1161A Cayuga Ave
Completed Mar 2024+1 unit on this lot · now 24 permits
Convert ground floor into ADU, two bedroom, one bath and kitchen space at 576 sq ft per state ADU program.
filed Aug 2022issued Mar 2023 · permit wait 7 monthscompleted Mar 2024 · built in 1 year
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$45,000
declared on the ADU permit
Permit wait
7 months
filed → issued
Build time
1 year
issued → completed
Builder
No contractor listed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Convert ground floor into ADU, two bedroom, one bath and kitchen space at 576 sq ft per state ADU program. 202208241212 | filed Aug 2022 · issued Mar 2023 · done Mar 2024 | $45k | city record |
| Revision | Revision to pa# 202208241212. Alter ADU entrance. Alter half bath in garage. 202307182416 · cites 202208241212 | filed Jul 2023 · issued Jul 2023 · done Mar 2024 | — | city record |
| Electrical | Upgrade 200amp overhead service and electrical lighting/outlet and remodel ADU. EW202305291448 | May 29, 2023 → Jan 18, 2024 | — | |
| Plumbing | 2 toilets, 3 sinks, 1 shower, 1 wash machine, 1 dryer. PP20230522057 | May 22, 2023 → Oct 13, 2023 | — |
1 other permit on this lot during the project, not counted
| Other | Remove and replace existing post on 1st flr due to damage. No changes to architectural. 202305238415 | filed May 2023 · issued May 2023 · done Feb 2024 | $5,000 | city record |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 6967, lot 024
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.