Converted · garage conversion · Presidio Heights

120 Commonwealth Ave

Completed Feb 2025+1 unit on this lot · now 15 permits

Conversion & renovation of existing detached garage into an ADU. New windows, new ext steps & frt porch, new ext finishes & lighting throughout. Int work incl modification & infill existing int walls, adding raised floor sys, new int partitions, doors, ceilings, & lighting. New kitchen, bathroom, & living space.

filed Aug 2023issued Feb 2024 · permit wait 6 monthscompleted Feb 2025 · built in 1 year
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$105,417
declared on the ADU permit
Permit wait
6 months
filed → issued
Build time
1 year
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitConversion & renovation of existing detached garage into an ADU. New windows, new ext steps & frt porch, new ext finishes & lighting throughout. Int work incl modification & infill existing int walls, adding raised floor sys, new int partitions, doors, ceilings, & lighting. New kitchen, bathroom, & living space.
202308235074 · Citywest Construction INC
filed Aug 2023 · issued Feb 2024 · done Feb 2025$105kcity record
ElectricalADU rewire.
EW202403237536
Mar 23, 2024 → May 21, 2024—
ElectricalPv solar plan# 6151 r1: 0 number of pv modules: 0 watts per module: 0 system (dc) kw: batteries: new subpanel: other: installing (2) enphase 10t batteries and (1) 200a enphase system controller/ transfer switch (1) 200a.
E202410187649
Oct 18, 2024 → Nov 26, 2024—
PlumbingWork category: 2pb; new kitchen and bathroom in ADU.
PW20240313314
Mar 13, 2024 → Jan 10, 2025—
PlumbingWork category: 1p; shower pan installation.
PW20241008178
Oct 8, 2024 → Oct 10, 2024—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 1064, lot 051
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map