Converted · garage conversion · Twin Peaks

120 Gardenside Dr

In progress+5 units on this lot · now 2117 permits

Add unit per ordinance 162-16. Convert existing garage space to new dwelling units, within existing envelope. New kitchen, baths, and entry doors. New windows visisble from street. Sprinkler & fire alarm under separat permit.

filed Mar 2017issued Mar 2023 · permit wait 6 years3 years 8 months since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$614,668 for 5 ADUs + other work
the permit also covers work unrelated to the ADU, so this is not an ADU price
Permit wait
6 years
filed → issued
Build time
in progress
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitAdd unit per ordinance 162-16. Convert existing garage space to new dwelling units, within existing envelope. New kitchen, baths, and entry doors. New windows visisble from street. Sprinkler & fire alarm under separat permit.
201703211956 · Sandbank Construction INC
filed Mar 2017 · issued Mar 2023$532kcity record
SprinklersExpand existing fire sprinkler system per nfpa 13, add 49 sprinklers, new 2" fire service -18ft.
202402135768 · Fire Guard Protection INC
filed Feb 2024 · issued Feb 2024 · done Oct 2024$42kcity record
Related permitUpgrade existing fire alarm system to comply with sffc section 1103. 7. 6. 1.
202403057157 · Crime Watch Security Sys Llc
filed Mar 2024 · issued Apr 2024 · done Oct 2024$40kcity record
SprinklersAs built ref pa# 202402135768 & 201703211956 (s1) fire sprinkler system- 49 sprinklers- 4 dus. 2" fire service-16 feet.
202403198108 · cites 201703211956 · Fire Guard Protection INC
filed Mar 2024 · issued Mar 2024—city record
ElectricalProvide and install a new 100 amp sub panel in unit #18. Bring electrical up to nec code 2024. Completely rewire entire unit.
EW202402156759
Feb 15, 2024 → Jan 10, 2025—
ElectricalProvide and install a new 100 amp sub panel. Bring electrical up to nec code 2024. Completely rewire entire unit.
EW202402156756
Feb 15, 2024 → Jan 10, 2025—
ElectricalProvide and install new 100 amp sub panel. Bring electrical up to nec code 2024. Completely rewire entire unit #17.
EW202402156757
Feb 15, 2024 → Oct 10, 2024—
ElectricalExtend the load side main disconnect to a termination can where it will be connected to a new four meter combo pack.
EW202402156758
Feb 15, 2024—
ElectricalProvide and install a new 100 amp sub panel in unit #19. Bring unit up to nec codes for 2024. Completely rewire entire unit.
EW202402156760
Feb 15, 2024 → Jan 10, 2025—
ElectricalOnline electrical permit: 4 of 4 - 9 floors. Installation of a fire alarm system by installing the fire panel, install all devices to be compatible with new facp and provide low frequency sounders in all sleeping areas to meet 75db at pillow to comply with sffd bulletin.
E202403193176
Mar 19, 2024 → Oct 10, 2024—
PlumbingWork category: 6pa; 4 new bathrooms, 4new kitchens, 4 new laundry washers.
PW20231020028
Oct 20, 2023 → Sep 23, 2024—
PlumbingWork category: 1m; installation of refrigeration lines, installation of drain lines, installation of control, wiring installation of 4 ceiling mounted heads min split and condensers.
PMW20240229975
Feb 29, 2024 → Oct 9, 2024—
PlumbingWork category: 4pa; install fire sprinkler system in lower floor new four ADU units per nfpa-13.
PW20240320488
Mar 20, 2024 → Oct 10, 2024—
PlumbingWork category: 8p; furnish and install 1x rheem proph40 t2 ru375-30 proterra water heater heat pump and connect to existing piping.
PW20240920752
Sep 20, 2024 → Oct 21, 2024—
PlumbingWork category: 8p; furnish and install one-x rheem proph40 t2 ru375-30 proterra water heater heat pum and connect to existing piping.
PW20240920756
Sep 20, 2024 → Oct 21, 2024—
PlumbingWork category: 8p; furnish and install 1x rheem proph40 t2 ru375-30 proterra water heater heat pump and connect to existing piping.
PW20240920753
Sep 20, 2024 → Oct 21, 2024—
PlumbingWork category: 8p; furnish and install one-x rheem proph40 t2 ru375-30 proterra water heater heat pum and connect to existing piping.
PW20240920755
Sep 20, 2024 → Oct 21, 2024—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 2854, lot 006
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map