Converted · interior conversion · Sunset/Parkside

1210 40th Ave

Completed Feb 2025+1 unit on this lot · now 25 permits

Convert existing livable space into ADU 500 SF, add new interior stairs, add new skylight in bathroom. Add power and office to main on ground 1st floor add new stairs between garage and main unit at 2nd floor.

filed Sep 2021issued Jul 2023 · permit wait 1 year 10 monthscompleted Feb 2025 · built in 1 year 6 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$280,000 + other work
the permit also covers work unrelated to the ADU, so this is not an ADU price
Permit wait
1 year 10 months
filed → issued
Build time
1 year 6 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitConvert existing livable space into ADU 500 SF, add new interior stairs, add new skylight in bathroom. Add power and office to main on ground 1st floor add new stairs between garage and main unit at 2nd floor.
202109218890 · Threemile Construction
filed Sep 2021 · issued Jul 2023 · done Feb 2025$280kcity record
ElectricalUnit 1210a: ADU, (1) bedroom, living room, kitchen, full bath; 15 lights, 10 switches, 23 receptacles, 3 fans, 1 dishwasher, 1 garbage disposal, 1 microwave, 1 range.
E202308118677
Aug 11, 2023 → Nov 12, 2024—
ElectricalUnit 1210: add (1) powder & office; 5 lights, 5 switches, 5 receptacles, 1 fan, 1 microwave.
E202308118681
Aug 11, 2023—
PlumbingTo obtain a final inspection for work approved under previous permit pm20230811417.
PM20241212540
Dec 12, 2024 → Dec 19, 2024—
PlumbingTo obtain a final inspection for work approved under previous permit pp20230811416.
PP20241212535
Dec 12, 2024 → Dec 19, 2024—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 1711, lot 025A
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map

Converted · interior conversion ADU at 1210 40th Ave · MiCasa