Converted · ground-floor conversion · Nob Hill

1234 Jones St

In progress+1 unit on this lot · now 2413 permits

Add 1 ADU at existing storage per ordinance 162-16.

filed Nov 2020issued Aug 2022 · permit wait 1 year 9 months4 years 3 months since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$115,000
declared across 2 permits: the ADU permit plus its sub-permits
Permit wait
1 year 9 months
filed → issued
Build time
in progress
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitAdd 1 ADU at existing storage per ordinance 162-16.
202011168987 · Sandbank Construction INC
filed Nov 2020 · issued Aug 2022$111kcity record
SprinklersRelocate 1 fire sprinkler in new trash room to center of room. Ref pa#2025-0715-0839.
202601204142 · Fault Line Plumbing INC
filed Jan 2026 · issued Jan 2026 · done Mar 2026$4,000city record
ElectricalUnit# 5. Kitchen & 1 bath rehab with washer dryer. 10 lights, 15 switches, 15 receptacles, 3 fans, 1 dishwasher, 1 garbage disposal, 1 microwave, 1 range.
E202210183057
Oct 18, 2022 → Feb 21, 2023—
ElectricalUnit# 18. 1 kitchen & 1 bath rehab. With washer dryer. 10 lights, 15 switches, 15 receptacles, 2 fans, 1 dishwasher, 1 garbage disposal, 1 microwave, 1 range.
E202210183060
Oct 18, 2022 → Feb 21, 2023—
ElectricalUnit 8: installation of washer and dryer.
E202211143579
Nov 14, 2022 → Dec 19, 2022—
ElectricalAt new trash room: relocate/rewire lights & switches. Install new booster fan for ventilation. (2) lights, (2) switches, (1) fan.
E202601288543
Jan 28, 2026 → Mar 25, 2026—
PlumbingKitchen & 1 bath rehab with washer dryer.
PP20221018655
Oct 18, 2022 → Feb 21, 2023—
PlumbingUnit# 18. 1 kitchen & 1 bath rehab.
PP20221018657
Oct 18, 2022 → Feb 21, 2023—
PlumbingUnit 8: installation of washer and dryer.
PP20221114127
Nov 14, 2022 → Dec 19, 2022—
PlumbingWork category: 8p; steam boiler replacement. Remove old boiler serial # 61-81064-1095 from record.
PW20231205064
Dec 5, 2023 → Jan 10, 2024—
PlumbingRelocate 1 fire sprinkler to center of new trash room.
PP20260120913
Jan 20, 2026 → Mar 18, 2026—
PlumbingAt new trash room: install new ventilation exhaust pipe from trashroom through lightwell and to roof. Install new bosoter fan per plans for exhaust. Install intake vent.
PM20260128060
Jan 28, 2026—
PlumbingWork category: 1p; water heater replacement.
PW20260331767
Mar 31, 2026 → Apr 27, 2026—
3 other permits on this lot during the project, not counted
Other#8: install one new clothes washer and dryer. No structural wall demo.
202208291500 · Ps2
filed Aug 2022 · issued Nov 2022 · done Dec 2022$4,500city record
OtherInstall roof access ladder, replace existing roof hatch with new. New 42" guardrail around new roof hatch.
202309277496 · Bay Area Activo INC
filed Sep 2023 · issued Feb 2024 · done Jun 2024$5,500city record
OtherRemodel existing storage room to meet requirements for use as a trash room.
202507150839 · Axel8 Construction LLC
· issued Oct 2025 · done Mar 2026$16kcity record

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 0221, lot 043
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map