Attached · Noe Valley
1279 Sanchez St
Completed Aug 2025+1 unit on this lot · now 28 permits
- new dwelling unit on first floor. - horizontal addition at rear first floor. - vertical addition to add third floor. - facade restoration & new exterior staircase to replace existing.
filed Dec 2021issued Aug 2023 · permit wait 1 year 8 monthscompleted Aug 2025 · built in 2 years
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$470,000 + other work
the permit also covers work unrelated to the ADU, so this is not an ADU price
Permit wait
1 year 8 months
filed → issued
Build time
2 years
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | - new dwelling unit on first floor. - horizontal addition at rear first floor. - vertical addition to add third floor. - facade restoration & new exterior staircase to replace existing. 202112204762 · Cook General Contractor INC | filed Dec 2021 · issued Aug 2023 · done Aug 2025 | $470k | city record |
| Electrical | Electrical work done in conjunction with general building permit application #202112204762. Scope of electrical work includes all new electrical done in conjunction with building renovation, and service upgrade to existing overhead service. EW202401296430 | Jan 29, 2024 → May 22, 2025 | — | |
| Electrical | Infrastructure permit for future rooftop photovoltaic solar system. EW202408210649 | Aug 21, 2024 → Apr 8, 2025 | — | |
| Electrical | Plan #6831. Residential solar. 10 pv modules, 425 watts per module, 4. 25 (dc) kw system. Batteries. E202412138802 | Dec 13, 2024 → Apr 8, 2025 | — | |
| Plumbing | Work category: 2pa; install radiant heat system. Install boiler and 50 gal indirect tank in garage. 3" flue to roof. PW20240822080 | Aug 22, 2024 → Jul 9, 2025 | — | |
| Plumbing | Work category: 1p; 2 shower pans. PW20241119248 | Nov 19, 2024 → Nov 21, 2024 | — | |
| Plumbing | Work category: 1m; install mini split. PMW20250114311 | Jan 14, 2025 → May 9, 2025 | — | |
| Plumbing | Work category: 1p; final inspection for permits pw20240318421 and pw20240321519. PW20250518341 | May 18, 2025 → Jul 9, 2025 | — |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 6552, lot 023
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.