Converted · ground-floor conversion · Oceanview/Merced/Ingleside

132 Sagamore St

In progress+1 unit on this lot · now 24 permits

Add an accessory dwelling unit per state ADU program, ordinance 162-16. New bedrooms, bathrooms, living room and kitchen at first floor.

filed Dec 2022issued Jun 2025 · permit wait 2 years 6 months1 year 5 months since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$180,000
declared on the ADU permit
Permit wait
2 years 6 months
filed → issued
Build time
in progress
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitAdd an accessory dwelling unit per state ADU program, ordinance 162-16. New bedrooms, bathrooms, living room and kitchen at first floor.
202212289312 · Ecowave INC
filed Dec 2022 · issued Jun 2025$180kcity record
ElectricalADU - electrical for kitchen and 3x bathroom, powder room, 3 bedrooms, dining room, and laundry room remodel.
E202603139594
Mar 13, 2026—
PlumbingInstall heat pump.
PM20260313936
Mar 13, 2026—
PlumbingADU- 3x bathroom, powder room, kitchen, laundry room, and replace 3 shower pans with underground work.
PP20260313935
Mar 13, 2026—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 7138, lot 012
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map