Converted · ground-floor conversion · Sunset/Parkside

1346 46th Ave

Completed Nov 2023+1 unit on this lot · now 25 permits

New ADU unit at ground floorno net increase of gross sq fttotal net increase of conditioned space is 32 sq ftreference structural permit #2021/0401/7736.

filed Feb 2021issued Oct 2022 · permit wait 1 year 8 monthscompleted Nov 2023 · built in 1 year 1 month
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$59,000
declared on the ADU permit
Permit wait
1 year 8 months
filed → issued
Build time
1 year 1 month
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitNew ADU unit at ground floorno net increase of gross sq fttotal net increase of conditioned space is 32 sq ftreference structural permit #2021/0401/7736.
202102104425 · Yu Kwan Construction Co
filed Feb 2021 · issued Oct 2022 · done Nov 2023$59kcity record
Related permitTo comply with nov #201783451 per hearing officer on 03/09/2021 - replace existing damaged concrete slab due to excavation at abutting neighbor at 1350 46th ave. No increase in building area, height, and envelope. Reference to ADU pa #202102104425.
202104017736 · cites 202102104425 · Speck Douglas Charles
filed Apr 2021 · issued May 2022 · done Oct 2023$110kcity record
ElectricalElectrical for two bedroo, 1 1/2 bathrom one kitchen in ground floor.
E202210213137
Oct 21, 2022 → Aug 10, 2023—
PlumbingPlumbing work for 1 1/2 bathroom and kitchen.
PP20221021726
Oct 21, 2022 → Aug 15, 2023—
PlumbingWork category: 1p; install heating system install #1 navien combi boiler to supply hot water & space heating install pex in joists install flue piping.
PW20230318522
Mar 18, 2023 → Jul 21, 2023—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 1800, lot 013
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map