Converted · ground-floor conversion · Bayview Hunters Point
1367 Gilman Ave
Completed Feb 2024+1 unit on this lot · now 26 permits
Comply with complaint#201935411. 1st floor: add ADU per ordinance 95-17. Add 1 kitchen, living, storage. 2 beds and 1. 5 bath.
filed May 2019issued Jul 2022 · permit wait 3 years 2 monthscompleted Feb 2024 · built in 1 year 7 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$95,244
declared across 3 permits: the ADU permit plus its sub-permits
Permit wait
3 years 2 months
filed → issued
Build time
1 year 7 months
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Comply with complaint#201935411. 1st floor: add ADU per ordinance 95-17. Add 1 kitchen, living, storage. 2 beds and 1. 5 bath. 201905201134 · C B S Construction INC | filed May 2019 · issued Jul 2022 · done Feb 2024 | $80k | city record |
| Revision | Revision to bpa#201905201134. 1st floor: reconfigure bathroom and add 1 full bath. 202208241205 · cites 201905201134 · C B S Construction INC | filed Aug 2022 · issued Sep 2022 · done Feb 2024 | $15k | city record |
| Address | Per pa #201905201134, add address to 2nd unit for ADU at apn 4941/028 as; 1367a gilman ave. M1229347 · cites 201905201134 | filed Nov 2022 · issued Nov 2022 | $244 | city record |
| Electrical | 1/f total remodel, 9 switches, 30 receptacles. E202209282688 | Sep 28, 2022 → Jan 30, 2024 | — | |
| Plumbing | New furnace. PM20220928290 | Sep 28, 2022 → Feb 15, 2023 | — | |
| Plumbing | Kitchen, 2 bathrooms, shower pan, undergroud plumbing, tankless water heater. PP20220928289 | Sep 28, 2022 → Feb 8, 2024 | — |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 4941, lot 028
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.