Converted · ground-floor conversion · Sunset/Parkside
1430 39th Ave
Completed Aug 2025+1 unit on this lot · now 25 permits
Convert part of existing ground floor into new ADU. New ADU will be 730 SF, to include 2 bedrooms, 2 full baths, kitchen, living room and storage. Site permit: no.
filed Nov 2021issued Apr 2024 · permit wait 2 years 5 monthscompleted Aug 2025 · built in 1 year 4 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$221,692
declared on the ADU permit
Permit wait
2 years 5 months
filed → issued
Build time
1 year 4 months
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Convert part of existing ground floor into new ADU. New ADU will be 730 SF, to include 2 bedrooms, 2 full baths, kitchen, living room and storage. Site permit: no. 202111031740 · Success Construction | filed Nov 2021 · issued Apr 2024 · done Aug 2025 | $222k | city record |
| Electrical | 40outlet 40lights. EW202406059145 | Jun 5, 2024 → Mar 20, 2025 | — | |
| Plumbing | Work category: 2pa; install new furance. PW20240605314 | Jun 5, 2024 → Mar 20, 2025 | — | |
| Plumbing | Work category: 2pa; install plumbing and gas line. PW20240605315 | Jun 5, 2024 → Jul 7, 2025 | — | |
| Plumbing | To amend pw20240605315: to add to original job scope - legalize ADU. PP20250707283 | Jul 7, 2025 → Jul 7, 2025 | — |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 1815, lot 009E
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.