Converted · ground-floor conversion · Inner Sunset
1443 12th Ave
In progress+1 unit on this lot · now 27 permits
Add new ADU to existing ground floor per gov. Code 65852. 2. To comply with nov #201281241.
filed Dec 2022issued Jun 2024 · permit wait 1 year 6 months2 years 4 months since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$273,919
declared across 2 permits: the ADU permit plus its sub-permits
Permit wait
1 year 6 months
filed → issued
Build time
in progress
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Add new ADU to existing ground floor per gov. Code 65852. 2. To comply with nov #201281241. 202212309489 · Odysseus Builders | filed Dec 2022 · issued Jun 2024 | $274k | city record |
| Address | Per pa #202212309489, add address to ADU at apn 1841/007 as; 1443a 12th ave for 2nd unit. M1234107 · cites 202212309489 | filed Jul 2024 · issued Jul 2024 | $419 | city record |
| Revision | Revision 202212309489- increase in scope: addition of kitchen cabinets bedroom cabinets led core lighting, egress door from ADU bedroom breakfast bar, layout of non load bearing walls. Location water heaters/electrical hvac reduction in scope. No fireplace installation no stairway rebuild. 202508223770 · cites 202212309489 · Odysseus Builders | filed Aug 2025 · issued Aug 2025 | — | city record |
| Electrical | New service line by pg&e to 200 amp. Ndw panel, new subpanel, new socket and light at ADU area. New ev at garage. 10 lights, 30 switches, 10 receptacles, 1 fan, 1 d/w, 1 g/d, 1 microwave. Ev charger. E202409237059 | Sep 23, 2024 → Aug 29, 2025 | — | |
| Electrical | Upgrade service main panel from 60amp to 400 amp. The basement be transformed into an ADU. Redmoel basement. Add two 40amp a/c. Add two electrical water heaters. Add ev charger. E202501079201 | Jan 7, 2025 → Aug 29, 2025 | — | |
| Plumbing | One 6 ton new heat pump split type ac with heat. PM20240923118 | Sep 23, 2024 → Aug 22, 2025 | — | |
| Plumbing | Replace new water line to 1 in copper pipe. Build 1 bathroom and kitchen, build ll 1 laundry, new underground drainage system. 2 sets tankless water heaters. . PP20240923117 | Sep 23, 2024 → Aug 22, 2025 | — |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 1841, lot 007
- Why we call it an ADU