1526A Masonic Ave
Completed Oct 2024+1 unit on this lot · now 19 permits
Construct one story type 5n, one story at 15' in height @ center of building at rear of 1526 masonic. New ADU under bpa@ 2020-0316-7178.
filed Mar 2020issued Jul 2022 · permit wait 2 years 4 monthscompleted Oct 2024 · built in 2 years 3 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$385,000
declared on the ADU permit
Permit wait
2 years 4 months
filed → issued
Build time
2 years 3 months
issued → completed
Builder
No contractor listed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Construct one story type 5n, one story at 15' in height @ center of building at rear of 1526 masonic. New ADU under bpa@ 2020-0316-7178. 202003167173 | filed Mar 2020 · issued Jul 2022 · done Oct 2024 | $385k | city record |
| Sprinklers | Revision to permit #202003167173: sprinkler requirement to be removed from scope of work per sb897 effective in san francisco 1/1/2023. Updated title 24 energy calcs. 202307061531 · cites 202003167173 | filed Jul 2023 · issued Oct 2023 · done Oct 2024 | — | city record |
| Electrical | 2. 88 kw roof mounted photovoltaic solar system flush mounted including (1) new 125a subpanel inside - 8 roof-mounted solar pv modules, 360 watts per module, 8 interactive inverter, total no. Of rating 2. 52 kw. EW202305191251 | May 19, 2023 → Jul 26, 2023 | — | |
| Electrical | 100 amp to 200 amp panel upgrade. EW202306071673 | Jun 7, 2023 → Jul 26, 2023 | — | |
| Electrical | ADU new wiring. EW202307172573 | Jul 17, 2023 → Jul 21, 2023 | — | |
| Electrical | ADU all new wiring. EW202401126141 | Jan 12, 2024 → Oct 8, 2024 | — | |
| Plumbing | Work category: 2pb; install new plumbing for ADU 1 bathroom1kitchen1 washer dryer. PW20230728896 | Jul 28, 2023 → Aug 23, 2024 | — | |
| Plumbing | Work category: 1p; install new radiant heat. PW20240227901 | Feb 27, 2024 → Aug 23, 2024 | — | |
| Plumbing | Work category: 1p; 1 shower pan. PW20240415097 | Apr 15, 2024 → May 28, 2024 | — |
1 other permit on this lot during the project, not counted
| Other | New retaining wall at property line. 202306079406 | filed Jun 2023 · issued Jun 2023 · done Oct 2024 | $45k | city record |
These permits also cite 202003167178, which the city filed before our records begin.
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 2616, lot 039
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.