Converted · ground-floor conversion · Inner Sunset

1527 10th Ave

Completed Aug 2026+0 units on this lot · now 26 permits

New ADU unit on the ground level.

filed Jul 2025issued Feb 2026 · permit wait 7 monthscompleted Aug 2026 · built in 6 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$88,000
declared across 2 permits: the ADU permit plus its sub-permits
Permit wait
7 months
filed → issued
Build time
6 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitNew ADU unit on the ground level.
202506118447 · Reliable Construction INC
filed Jul 2025 · issued Feb 2026 · done Aug 2026$80kcity record
RevisionRevision to pa 202506118447 expand unit @ 1st floor to add bedroom to ADU.
202604290356 · cites 202506118447 · Reliable Construction INC
filed Apr 2026 · issued May 2026 · done Jul 2026$8,000city record
ElectricalKitchen, bath, laundry, studio upgrade, new subpanel. 100 amp subpanel, 11 lights, 12 switches, 12 receptacles, 2 fans, 1 d/w, 1 g/d, 1 microwave, 1 range, 2 s/d.
E20260402070
Apr 2, 2026 → Jul 16, 2026—
ElectricalService upgrade from 225 amp to 400amp. Adding one more meter section for a total of 4 meter sections.
EW202604054012
Apr 5, 2026—
PlumbingInstall new mini-split system.
PM20260402319
Apr 2, 2026 → Jul 24, 2026—
PlumbingKitche, bath, laundry upgrade. Shower pan, no underground work.
PP20260402317
Apr 2, 2026 → Jul 16, 2026—
1 other permit on this lot during the project, not counted
OtherReroof hot works.
202605261830 · Highland Construction S F INC
filed May 2026 · issued May 2026 · done May 2026$14kcity record

Trade permits show what work was done and when; the city does not record who pulled them.