Converted · garage conversion · Bayview Hunters Point

1527A Palou Ave

In progress+1 unit on this lot · now 23 permits

Convert existing garage and storage space to one ADU unit at the ground floor per the state ADU program. Approximately 980sf.

filed Jun 2022issued Aug 2025 · permit wait 3 years 2 months1 year 3 months since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$248,163
declared on the ADU permit
Permit wait
3 years 2 months
filed → issued
Build time
in progress
issued → completed
Builder
No contractor listed

Permits in this project

PermitWhatWhenDeclared
ADU permitConvert existing garage and storage space to one ADU unit at the ground floor per the state ADU program. Approximately 980sf.
202206136217
filed Jun 2022 · issued Aug 2025$248kcity record
ElectricalGeneral wiring.
EW202605195021
May 19, 2026—
ElectricalGeneral wiring.
EW202605295258
May 29, 2026 → Jun 25, 2026—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 5326, lot 023
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map

Converted · garage conversion ADU at 1527A Palou Ave · MiCasa