1551A 43rd Ave
In progress+1 unit on this lot · now 25 permits
Legalize unpermitted kitchen to be new ADU on ground floor per 162-16.
filed Aug 2022issued Dec 2025 · permit wait 3 years 4 months11 months since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$70,000
declared on the ADU permit
Permit wait
3 years 4 months
filed → issued
Build time
in progress
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Legalize unpermitted kitchen to be new ADU on ground floor per 162-16. 202208220958 · Y & W Construction Co | filed Aug 2022 · issued Dec 2025 | $70k | city record |
| Electrical | Unit a: install 200 a new meter. E202608032578 | Aug 3, 2026 | — | |
| Electrical | Unit a: revision to permit e202608032578, add scope, install lights in kitchen, gfci outlets, gas stove, dishwasher, dryer, install lights in garage, hall ways, install 3 220v electric heaters. E202609013260 | Sep 1, 2026 | — | |
| Plumbing | Unit a: install gas meter and gas line, new gas line. PP20260803587 | Aug 3, 2026 | — | |
| Plumbing | Unit a: revision to pp20260803587: add scope, install kitchen sink, washer, dryer, gas water heater, dishwasher. PP20260901245 | Sep 1, 2026 | — |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 1889, lot 010
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.