Converted · garage conversion · Lone Mountain/USF
1552A Fulton St
Completed Jan 2024+1 unit on this lot · now 39 permits
At the existing front building on the lot, per california government code 65852. 2, add a new a. D. U. In existing garage and storage space at ground floor.
filed Sep 2021issued Feb 2022 · permit wait 5 monthscompleted Jan 2024 · built in 1 year 11 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$172,200
declared across 3 permits: the ADU permit plus its sub-permits
Permit wait
5 months
filed → issued
Build time
1 year 11 months
issued → completed
Builder
Deep Elm Construction LLCAlso on this project: Chung Wah Plumbing & Fire Protection, K K Electric & Alarm Company
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | At the existing front building on the lot, per california government code 65852. 2, add a new a. D. U. In existing garage and storage space at ground floor. 202109178680 · Deep Elm Construction LLC | filed Sep 2021 · issued Feb 2022 · done Jan 2024 | $142k | city record |
| Sprinklers | Installation of fire sprinkler system for entire 1/f(ground). Underground service included. 202204011381 · Chung Wah Plumbing & Fire Protection | filed Apr 2022 · issued May 2022 | $26k | city record |
| Sprinklers | Install a fire sprinkler flow monitoring system for fire sprinklers (nfpa13r) installed under pa#202204011381. 202209303534 · K K Electric & Alarm Company | filed Sep 2022 · issued Sep 2022 · done Dec 2022 | $3,800 | city record |
| Electrical | Provide electrical for new ADU at 1/f, 2 new bath, 1 kitchen. 10 lights, 10 switches, 30 receptalces, 3 fans, 1 dishwahser, 1 g/d, 1 microwave, 5 smoke detectors. E202203179019 | Mar 17, 2022 → Dec 14, 2023 | — | |
| Electrical | Remodel. Upgrade as needed. E202207261555 | Jul 26, 2022 → Jul 27, 2022 | — | |
| Electrical | Install fire sprinkler flow monitor alarm plan. E202209302741 | Sep 30, 2022 → Dec 2, 2022 | — | |
| Plumbing | Provide plumbing for new ADU at g/f, 2 bath, 1 kitchen. PP20220317755 | Mar 17, 2022 → Jul 27, 2022 | — | |
| Plumbing | Work category: 4pa; final inspection. PW20221209206 | Dec 9, 2022 → Dec 13, 2022 | — | |
| Plumbing | To obtain final inspection for work approved under permit application# pp20210827003 (original scope: remodel 2 units upgrade as needed). PP20240125012 | Jan 25, 2024 → Jan 30, 2024 | — |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 1177, lot 016
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.