Construct (3) ADU per ord 162-16. Remove existing hss & replace with new foundations & moment frames #1-4 & to add footing for new load bearing wall & to add footing @ lobby/garage.
filed Feb 2020issued May 2022 · permit wait 2 years 2 monthscompleted Nov 2024 · built in 2 years 6 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$471,135 for 3 ADUs
one permit, 3 units; not a per-unit price
Permit wait
2 years 2 months
filed → issued
Build time
2 years 6 months
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Construct (3) ADU per ord 162-16. Remove existing hss & replace with new foundations & moment frames #1-4 & to add footing for new load bearing wall & to add footing @ lobby/garage. 202002265525 · H Construction Co | filed Feb 2020 · issued May 2022 · done Nov 2024 | $375k | city record |
| Sprinklers | Install new fire sprinler system per nfpa13 througout ground floor including 2in deidcated fire servce nfpa 24. Ref pa 202002265525. 202208251248 · cites 202002265525 · Firemex Solutions INC | filed Aug 2022 · issued Aug 2022 · done Oct 2023 | $47k | city record |
| Sprinklers | Upgrade existing fire alarm system to comply with sffc section 1103. 7. 6. 1 and include sprinkler monitoring. Ref pa#202002265525. Ref sprinkler #202208251248. 202209162602 · cites 202002265525 · Crime Watch Security Sys Llc | filed Sep 2022 · issued Sep 2022 · done Oct 2023 | $49k | city record |
| Revision | Administrative permit only to show as-built conditions of units/building per district bid. Ref pa# 202002265525 (ADU), 22103317632 (#11), 20209033429 (#10), 201911307765 (#9), 201911207764 (#7), 201911207762 (#6), 202010217083 (#5), 201911207761 (#4), 201911207760 (#3), 202211307385 (#2). 202308214889 · cites 202002265525 · H Construction Co | filed Aug 2023 · issued Dec 2023 · done Nov 2024 | — | city record |
| Electrical | New ADU c: 2 bedrooms, 1 living room, 1 kitchen, 2 baths, 1 laundry. New plugs, lights, switches, new subpanel. E20220513214 | May 13, 2022 → Oct 13, 2023 | — | |
| Electrical | House - 1 garbage room. New lights, switches, plugs, 5 exit lights. E20220513215 | May 13, 2022 → Oct 5, 2023 | — | |
| Electrical | New ADU a: 2 bedrooms, 1 living room, 1 kitchen, 2 baths, 1 laundry. New plugs, lights, switches, new subpanel. E20220513212 | May 13, 2022 → Oct 13, 2023 | — | |
| Electrical | New ADU b: 3 bedrooms, 1 living room, 1 kitchen, 2 baths, 1 laundry. New plugs, lights, switches, new subpanel. E20220513213 | May 13, 2022 → Oct 12, 2023 | — | |
| Electrical | Electrical service ufer method. E202212144069 | Dec 14, 2022 → Dec 19, 2022 | — | |
| Electrical | To obtain final inspection for previous permit e202009309814 (unit#6). E202212154096 | Dec 15, 2022 → Oct 31, 2024 | — | |
| Electrical | To obtain final inspection for previous permit e202108255241 (unit#5). E202212154097 | Dec 15, 2022 → Dec 19, 2022 | — | |
| Electrical | To obtain final inspection for previous permit e202009309813 unit#3. E202212154098 | Dec 15, 2022 → Dec 19, 2022 | — | |
| Electrical | Renewal of permit #ew202107136975- upgrade service fee charge per inspector van koll. E202212154102 | Dec 15, 2022 → Aug 23, 2024 | — | |
| Electrical | Obtain permit for final inspection only, ref #ew202012222421 - modification of existing fire alarm system. EW202212197919 | Dec 19, 2022 → Oct 27, 2023 | — | |
| Electrical | Unit 2: remodel and convert to 3 bedrooms, 2 baths, 1 kitchen and 1 laundry. E202303035364 | Mar 3, 2023 → Oct 13, 2023 | — | |
| Electrical | Install 3 ceiling lights 1 ceiling fan 3 outlets. E202405244612 | May 24, 2024 → Nov 4, 2024 | — | |
| Plumbing | Plumbing for new ADU a/b/c: a - 2 baths, 1 laundry, 1k itchen, 1 d/w. ADU b: 2 baths, 1 laundry, 1 kitchen, 1 d/w. ADU c: 1 bath, 1 laundry, 1 kitchen, 1/dw. House: 1 garbage room, 5 hose bibs. PP20220513850 | May 13, 2022 → Dec 16, 2022 | — | |
| Plumbing | Install new fire sprinler system per nfpa13 througout ground floor including 2in deidcated fire servce nfpa 24. Ref pa 202002265525. PP20220829774 | Aug 29, 2022 → Oct 10, 2023 | — | |
| Plumbing | Work category: 8p; this project includes a new hot water heating system with 1 boiler and baseboard convectors in each of 10 units. There is also a new dhw system with 2 tankless water heaters and a storage tank. PW20221024985 | Oct 24, 2022 → Sep 19, 2024 | — | |
| Plumbing | Unit 2: 2 new bath, 1 new kitchen and 1 new laundry. PP20230303777 | Mar 3, 2023 → Sep 19, 2023 | — | |
| Plumbing | Install 2 tankless water heater. PP20240524021 | May 24, 2024 → Oct 4, 2024 | — |
2 other permits on this lot during the project, not counted
| Other | 2nd flr - unit 2 remodel - relocate existing kitchen & bath, remodel bedroom, add 1 bath & 2 bedroom per plan. 202211307385 · H Construction Co | filed Nov 2022 · issued Mar 2023 · done Aug 2024 | $254k | city record |
| Other | To obtain final inspection for work approved under pa# 202409092051, 201911207762, and 202008182007. All work is complete. 202411054419 · H Construction Co | filed Nov 2024 · issued Nov 2024 · done Nov 2024 | — | city record |
These permits also cite 201911307765, 201911207764, 201911207762, 202010217083, 201911207761, 201911207760, 202409092051, 202008182007, which the city filed before our records begin.
Trade permits show what work was done and when; the city does not record who pulled them.