Converted · ground-floor conversion · Marina

1556A Lombard St

Completed Apr 2026+2 units on this lot · now 611 permits

Addition of 2 new units(ADU) on the first floor (per local ADU program): 1556a: 1-living room, 1-bedroom, 1 bathroom, 1-kitchen (691 sq ft) 1556b: 1-living room, 2-bedrooms, 1 bathroom, 1-kitchen (866 sq ft).

filed Mar 2021issued Oct 2024 · permit wait 3 years 7 monthscompleted Apr 2026 · built in 1 year 6 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$297,700 for 2 ADUs
one permit, 2 units; not a per-unit price
Permit wait
3 years 7 months
filed → issued
Build time
1 year 6 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitAddition of 2 new units(ADU) on the first floor (per local ADU program): 1556a: 1-living room, 1-bedroom, 1 bathroom, 1-kitchen (691 sq ft) 1556b: 1-living room, 2-bedrooms, 1 bathroom, 1-kitchen (866 sq ft).
202103086117 · S L M Development INC
filed Mar 2021 · issued Oct 2024 · done Apr 2026$209kcity record
Related permitRev 202103086117- rear unit 1556b- change in entry layout. New concrete slab.
202411225582 · cites 202103086117 · S L M Development INC
filed Nov 2024 · issued Dec 2024 · done Apr 2026$50kcity record
SprinklersUpgrade existing fire alarm system to comply with sffc section 1103. 7. 6. 1 and include sprinkler monitoring.
202505086112 · Crime Watch Security Sys Llc
filed May 2025 · issued May 2025 · done Jan 2026$39kcity record
RevisionNew pg&e large panel board construction with struts. Revision to landscape layout per 202103086117.
202506118475 · cites 202103086117 · S L M Development INC
filed Jun 2025 · issued Jul 2025 · done Apr 2026$600city record
ElectricalUnit a: add (2) adus on the first floor.
E202410177601
Oct 17, 2024 → Feb 13, 2026—
ElectricalUnit b: add (4) adus on the first floor.
E202410177602
Oct 17, 2024 → Feb 13, 2026—
ElectricalUpgrade the existing panel from 200 amps to 400 amps. Reference ADU permit e202410177601 & e202410177602.
E202508295176
Aug 29, 2025—
ElectricalOnline electrical permit: 120 of buildings of 7-12 dwelling units. Modification of an existing fire alarm system including sprinkler monitoring by upgrading the fire panel, update all existing devices to be compatible with new facp and provide low frequency sounders in.
E202512167790
Dec 16, 2025 → Jan 9, 2026—
ElectricalRef: witness test fees for final inspection for e202512167790.
EW202601091924
Jan 9, 2026 → Jan 12, 2026—
PlumbingUnit 1556 & 1556b: addition 2 adus to the first floor (1 kitchen + 1 bath + 1 laundry) for each unit. Underground work.
PP20241017532
Oct 17, 2024 → Mar 25, 2026—
PlumbingOutdated furnace systems to eb removed and relocated with high efficiency furnace systems. (8) total units.
PM20250115001
Jan 15, 2025 → Feb 17, 2026—
2 other permits on this lot during the project, not counted
OtherRecommencement and completion of work approved under pa # 2022-0118-6139.
202503111969 · S L M Development INC
filed Mar 2025 · issued Mar 2025 · done Apr 2025$30kcity record
OtherSubmit the as built structural drawing. Ref 202306210515.
202604079012 · S L M Development INC
filed Apr 2026 · issued Apr 2026 · done Apr 2026—city record

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 0497, lot 006C
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map