Converted · legalization · Presidio Heights
155A Mayfair Dr
Completed Apr 2022+1 unit on this lot · now 27 permits
Existing unit built in 2008, no records of permitting. We are submitting documentation for legalization. Unit is 811 sq approx with: 1 bedroom, 1 full bathroom, 1 kitchen, independent access from street. One of the existing windows needs to be altered to comply with cbc 1030.
filed Apr 2021issued Oct 2021 · permit wait 5 monthscompleted Apr 2022 · built in 6 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$120,000
declared on the ADU permit
Permit wait
5 months
filed → issued
Build time
6 months
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Existing unit built in 2008, no records of permitting. We are submitting documentation for legalization. Unit is 811 sq approx with: 1 bedroom, 1 full bathroom, 1 kitchen, independent access from street. One of the existing windows needs to be altered to comply with cbc 1030. 202104309637 · Daly Connor Corporation | filed Apr 2021 · issued Oct 2021 · done Apr 2022 | $120k | city record |
| Electrical | Lower level: legalization of habitable space including bedroom, bathroom. Kitchen. Remodel existing bathroom upstairs. E202110206248 | Oct 20, 2021 → Apr 4, 2022 | — | |
| Electrical | Legalzation of existing unit under pa202104309637. E202112067150 | Dec 6, 2021 → Mar 2, 2022 | — | |
| Plumbing | Remodel of unit including a new bathroom an remodel of existing with shower pan. Including kitchen. All plumbing as necessary to bring up to code. PP20211020998 | Oct 20, 2021 → Mar 2, 2022 | — | |
| Plumbing | Amend to pp20211020998: additional work scope description: add new 1-1/4in water service line. PP20211213989 | Dec 13, 2021 → Dec 20, 2021 | — | |
| Plumbing | Install split level heating. PM20220302419 | Mar 2, 2022 → Mar 7, 2022 | — | |
| Plumbing | Legalize existing ADU. PP20220302418 | Mar 2, 2022 → Mar 7, 2022 | — |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 1041, lot 001
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.