Add studio ADU per state mandated program. Total ADU area is 262 SF.
filed Jun 2021issued Aug 2022 · permit wait 1 year 3 monthscompleted May 2024 · built in 1 year 9 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$40,000
declared across 2 permits: the ADU permit plus its sub-permits
Permit wait
1 year 3 months
filed → issued
Build time
1 year 9 months
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Add studio ADU per state mandated program. Total ADU area is 262 SF. 202106152428 · Fox Brothers Construction INC | filed Jun 2021 · issued Aug 2022 · done May 2024 | $30k | city record |
| Sprinklers | Install 12- sprinklers throughout ground floor, per nfpa13, underground per nfpa24. Ref pa# 2021-0615-2428. 202308154411 · cites 202106152428 · P P Plumbing | filed Aug 2023 · issued Sep 2023 · done Apr 2024 | $10k | city record |
| Electrical | New ADU rewire. EW202303209780 | Mar 20, 2023 → Apr 5, 2024 | — | |
| Electrical | Bath rewire part kitchen add plugs to upper bedrooms. EW202309213978 | Sep 21, 2023 → Apr 5, 2024 | — | |
| Plumbing | Work category: 2pa; rough in bathroom and kitchen on ground floor. PW20230907949 | Sep 7, 2023 → Mar 21, 2024 | — | |
| Plumbing | Work category: 4pa; install 12 fire sprinkler heads (ground floor only. PW20230912063 | Sep 12, 2023 → Apr 16, 2024 | — |
Trade permits show what work was done and when; the city does not record who pulled them.