Converted · legalization · Sunset/Parkside

1579 46th Ave

Completed Dec 2024+1 unit on this lot · now 26 permits

Comply with nov#202172415. Legalize existing dwelling unit. Upgrade fire separation between units common space. ADU per ord no. 162-16 + new deck.

filed Jul 2022issued Jan 2024 · permit wait 1 year 6 monthscompleted Dec 2024 · built in 10 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$51,000
declared on the ADU permit
Permit wait
1 year 6 months
filed → issued
Build time
10 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitComply with nov#202172415. Legalize existing dwelling unit. Upgrade fire separation between units common space. ADU per ord no. 162-16 + new deck.
202207299611 · Rodas Construction
filed Jul 2022 · issued Jan 2024 · done Dec 2024$51kcity record
RevisionRevision to pa 202207299611 - revision of material for (1) window and sliding glass door at back of house to vinly from aluminum.
202402286708 · cites 202207299611
filed Feb 2024 · issued Feb 2024 · done Dec 2024—city record
ElectricalRef to building pa #202207299611 legalize ADU: 1 bath, 1 kitchen, & 1 bedroom. New bathroom fan & smoke alarm.
E202404103659
Apr 10, 2024 → Jul 17, 2024—
PlumbingRef to building pa #202207299611 legalize ADU: 1 bath, 1 kitchen, & 1 bedroom. New gas line for gas heater, new sink.
PP20240410275
Apr 10, 2024 → Nov 20, 2024—
PlumbingCheck south pipe.
PM20240604177
Jun 4, 2024 → Nov 12, 2024—
PlumbingTo ammend pp20240410275 to include water heater.
PP20240604178
Jun 4, 2024 → Nov 20, 2024—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 1892, lot 008B
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map