Converted · legalization · Sunset/Parkside
1587 43rd Ave
Completed Dec 2022+1 unit on this lot · now 24 permits
Ledu: legalize existing 815 SF dwelling unit at ground floor.
filed Feb 2021issued May 2022 · permit wait 1 year 3 monthscompleted Dec 2022 · built in 7 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$25,000
declared on the ADU permit
Permit wait
1 year 3 months
filed → issued
Build time
7 months
issued → completed
Builder
No contractor listed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Ledu: legalize existing 815 SF dwelling unit at ground floor. 202102114461 | filed Feb 2021 · issued May 2022 · done Dec 2022 | $25k | city record |
| Electrical | New kitchen, 6 gfci, refrig, micrwave, oven hood, dishwasher, garage disposal. 1 dishwasher, 1 g/d, 1 microwave, 1 range/oven. E20220519317 | May 19, 2022 → Dec 6, 2022 | — | |
| Plumbing | One new furnace in garage, 1 kitchen hood. PM20220519953 | May 19, 2022 → Dec 7, 2022 | — | |
| Plumbing | One bathroom and one kitchen to be removed. New kitchen plumbing with underground work. PP20220519952 | May 19, 2022 → Dec 7, 2022 | — |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 1889, lot 018B
- Why we call it an ADU
- Two independent model reviewers agreed the permit creates an ADU: “"ledu: legalize existing 815 sf dwelling unit at ground floor"; units 1 → 2, use 1 family dwelling → 2 family dwelling”