Converted · ground-floor conversion · Bernal Heights

15A Joy St

Completed Aug 2024+1 unit on this lot · now 18 permits

Convert entire lowest floor of existing new (unbuilt) single family house to add a 1 bedroom ADU.

filed Nov 2020issued Apr 2022 · permit wait 1 year 5 monthscompleted Aug 2024 · built in 2 years 5 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$20,000
declared on the ADU permit
Permit wait
1 year 5 months
filed → issued
Build time
2 years 5 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitConvert entire lowest floor of existing new (unbuilt) single family house to add a 1 bedroom ADU.
202011199289 · Ace Drilling & Excavation
filed Nov 2020 · issued Apr 2022 · done Aug 2024$20kcity record
RevisionResidential fire sprinlkers system. As-built: chg private underground from 2" to 1. 5" incl calcs. 13d combo system. Ref pa 202204121995.
202306129819 · North Star Plumbing & Fire Protection INC
filed Jun 2023 · issued Jun 2023 · done Apr 2024—city record
ElectricalWiring of ADU unit. 1 bedroom 1 bath.
EW202304170410
Apr 17, 2023 → May 21, 2024—
Electrical320 amp service underground.
EW202311105118
Nov 10, 2023 → May 21, 2024—
PlumbingWork category: 1p; 1 shower pan.
PW20220426929
Apr 26, 2022 → May 3, 2022—
PlumbingWork category: 2pb; scope of working includes plumbing for 1 full bathroom, 1 shower pan, 1 kitchen and 1 laundry room. As well as the underground water and sewer to street main.
PW20230419368
Apr 19, 2023 → Mar 20, 2024—
PlumbingWork category: 1p; 1 shower pan.
PW20230710357
Jul 10, 2023 → Jul 13, 2023—
PlumbingRenewal for pw20211007455. Same work scope for final inspection. Work category: 4pa; installation of new fire sprinkler system.
PP20240319868
Mar 19, 2024 → Mar 20, 2024—
1 other permit on this lot during the project, not counted
OtherRef pa# 202012301906. Replace glass railing at roof deck with metal railings (42" high + 4" o. C. Balusters).
202305127710 · Ace Drilling & Excavation
filed May 2023 · issued May 2023 · done Aug 2024—city record

These permits also cite 202012301906, which the city filed before our records begin.

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 5577, lot 005
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house