Converted · legalization · West of Twin Peaks

15A Merced Ave

Completed Apr 2023+1 unit on this lot · now 25 permits

Addition of dwelling unit per ord no 162-16. No exterior changes. Comply with planning complaints #2017-014858 enf & #2018-002800 enf.

filed Apr 2018issued Nov 2021 · permit wait 3 years 6 monthscompleted Apr 2023 · built in 1 year 5 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$14,000
declared on the ADU permit
Permit wait
3 years 6 months
filed → issued
Build time
1 year 5 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitAddition of dwelling unit per ord no 162-16. No exterior changes. Comply with planning complaints #2017-014858 enf & #2018-002800 enf.
201804267535 · Joe 88 Construction Company
filed Apr 2018 · issued Nov 2021 · done Apr 2023$14kcity record
RevisionRevision to permit 201804267535. Reconfigure interior layouts. Add 2 bathrooms and non bearing partition walls per plan.
202209011731 · cites 201804267535 · Joe 88 Construction Company
filed Sep 2022 · issued Sep 2022 · done Apr 2023$20kcity record
ElectricalAdd ADU at 1st floor. New wiring and lighting. Add sub-panel.
E202203108898
Mar 10, 2022 → Mar 20, 2023—
PlumbingRelocate furnace and flue pipe.
PM20220310617
Mar 10, 2022 → Feb 9, 2023—
PlumbingAdd ADU at 1st floor. Kitchen, (4) bath and laundry. 4 shower pan installations.
PP20220310616
Mar 10, 2022 → Feb 9, 2023—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 2877, lot 015
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map