Converted · ground-floor conversion · Marina
1612 Vallejo St
Completed Feb 2023+1 unit on this lot · now 26 permits
Add a code-compliant unit at ground floor; enclosure a rear portion at the side of the structure.
filed Mar 2020issued Oct 2021 · permit wait 1 year 7 monthscompleted Feb 2023 · built in 1 year 3 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$150,000
declared on the ADU permit
Permit wait
1 year 7 months
filed → issued
Build time
1 year 3 months
issued → completed
Builder
Gil Construction & Associates IncorporatedAlso on this project: Christopher Gate Construction INC
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Add a code-compliant unit at ground floor; enclosure a rear portion at the side of the structure. 202003116795 · Gil Construction & Associates Incorporated | filed Mar 2020 · issued Oct 2021 · done Feb 2023 | $150k | city record |
| Revision | Revision to bpa#202003116795, move partition wall to expand bath. 202209162590 · cites 202003116795 · Christopher Gate Construction INC | filed Sep 2022 · issued Sep 2022 · done Feb 2023 | — | city record |
| Electrical | Legalize existing wiring in the garage level living space. EW202111269917 | Nov 26, 2021 → Dec 3, 2021 | — | |
| Electrical | Bathroom remodeling. EW202210186695 | Oct 18, 2022 → Jan 9, 2023 | — | |
| Plumbing | Work category: 1p; rough in and trim out bathroom on bottom floor. 1 toilet, 1 sink, 1 shower. PW20220929326 | Sep 29, 2022 → Jan 30, 2023 | — | |
| Plumbing | (1) shower pan. PP20221018645 | Oct 18, 2022 → Jan 30, 2023 | — |
Trade permits show what work was done and when; the city does not record who pulled them.