Converted · ground-floor conversion · Noe Valley

1616 Noe St

Completed May 2024+2 units on this lot · now 412 permits

Rear building: addition of two units on 1st flr per ord# 162-16. Unit a=726 sqsf with 1 living rm, 1 kitchen, 1 bath, and 2 bedrms. Unit b=645 sqsf with 1 living rm, 1 kitchen, 1 bath and 2 bedrms. Voluntary seismic retrofit under bpa# 2020-0109-1521.

filed Feb 2020issued Dec 2022 · permit wait 2 years 10 monthscompleted May 2024 · built in 1 year 5 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$182,300 for 2 ADUs + other work
the permit also covers work unrelated to the ADU, so this is not an ADU price
Permit wait
2 years 10 months
filed → issued
Build time
1 year 5 months
issued → completed
Builder
No contractor listed

Permits in this project

PermitWhatWhenDeclared
ADU permitRear building: addition of two units on 1st flr per ord# 162-16. Unit a=726 sqsf with 1 living rm, 1 kitchen, 1 bath, and 2 bedrms. Unit b=645 sqsf with 1 living rm, 1 kitchen, 1 bath and 2 bedrms. Voluntary seismic retrofit under bpa# 2020-0109-1521.
202002104043
filed Feb 2020 · issued Dec 2022 · done May 2024$150kcity record
AddressAdd 2 address - 1616a & 1616b for ADU pa #202002104043.
M1231847 · cites 202002104043
filed Sep 2023 · issued Sep 2023—city record
SprinklersInstall new fire sprinkler system throughout new units per nfpa13-r including dedicated fire service per nfpa24, total 23 sprinklers. Ref pa# 202002104043.
202310309728 · cites 202002104043 · Rodriguez Fire Protection
filed Oct 2023 · issued Oct 2023 · done May 2024$24kcity record
SprinklersInstallation of a new sprinkler monitoring system. Ref pa #202310309728.
202404049372 · Crime Watch Security Sys Llc
filed Apr 2024 · issued Apr 2024 · done May 2024$8,400city record
ElectricalBpa#202002104043 unit a: new electrical throughout for new ADU: 1-bathrooms, 1-kitchens, 2-bedrooms, and 1-with d.
E202308108652
Aug 10, 2023 → Apr 12, 2024—
ElectricalBpa#202002104043 unit b: new electrical throughout for new ADU: 1-bathrooms, 1-kitchens, 2-bedrooms, and 1-with d.
E202308108653
Aug 10, 2023 → Apr 12, 2024—
ElectricalCorrect address from 1600 to 1616-1618 noe st. Unit b.
E202308148716
Aug 14, 2023 → Sep 19, 2025—
ElectricalTo correct address from 1600 noe to 1616-1618 noe st. Unit a. Ref pa# e202308108652.
E202308148715
Aug 14, 2023 → Sep 19, 2025—
ElectricalService upgrade for 400amp panel for 4 meters aic rating for breaker 22k.
E202401101678
Jan 10, 2024 → May 20, 2024—
ElectricalOnline electrical permit: 60 of buildings of 6 dwelling units or less. Installation of a sprinkler monitoring system.
E202404253989
Apr 25, 2024 → May 8, 2024—
PlumbingTo correct address from 1600 t0 1616-1618 noe st. Ref pa#pp20230810394.
PP20230814443
Aug 14, 2023 → Apr 26, 2024—
PlumbingWork category: 4pa; install new 13r fire sprinkler system of 21 heads.
PW20231109558
Nov 9, 2023 → May 13, 2024—

These permits also cite 202001091521, which the city filed before our records begin.

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 6630, lot 001
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map