Converted · garage conversion · Bayview Hunters Point
1655 Revere Ave
Completed Dec 2025+1 unit on this lot · now 38 permits
Add one ADU at the rear of the garage on the ground floor of an existing 2-unit, three story building. The new unit will be two bedroom with a kitchen and two baths. No variances are required or requested.
filed Nov 2021issued Jul 2024 · permit wait 2 years 8 monthscompleted Dec 2025 · built in 1 year 5 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$184,196
declared across 3 permits: the ADU permit plus its sub-permits
Permit wait
2 years 8 months
filed → issued
Build time
1 year 5 months
issued → completed
Builder
Threemile ConstructionAlso on this project: Best Care Fire Protection, Poly - On Electrical, American Standard Roofing INC
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Add one ADU at the rear of the garage on the ground floor of an existing 2-unit, three story building. The new unit will be two bedroom with a kitchen and two baths. No variances are required or requested. 202111011562 · Threemile Construction | filed Nov 2021 · issued Jul 2024 · done Dec 2025 | $150k | city record |
| Sprinklers | Install a new fire sprinkler system per nfpa 13 through out entire 1st floor including 2 inch dedicated fire service total 26 heads ref pa#2021-1101-1562. 202501138173 · cites 202111011562 · Best Care Fire Protection | filed Jan 2025 · issued Jan 2025 · done Jun 2025 | $27k | city record |
| Sprinklers | Install a new dedicated fa system (sprinkler monitoring) per nfpa 72-2022 section 23. 8. 5. 5. 1 with (1) fire alarm control unit (1) wireless commerical fire communicator (1) smoke detector above the facu (1) manual pull station referenece per nfpa13#: 202501138173. 202505206834 · Poly - On Electrical | filed May 2025 · issued May 2025 · done Jun 2025 | $7,000 | city record |
| Electrical | Unit#1655(a) add ADU: two bedrooms, 1 kitchen, and two bathrooms. E202407255853 | Jul 25, 2024 → Jul 24, 2025 | — | |
| Electrical | 1655-1657 revere ave install a new sprinkler monitoring system per nfpa-2022 section 23. 8. 5. 5. 1 reference sprinkler per nfpa 13 #2025-0113-8173. E202505292786 | May 29, 2025 → Jun 23, 2025 | — | |
| Plumbing | Relocated existing two furnaces to garage. PM20240725078 | Jul 25, 2024 → Nov 7, 2025 | — | |
| Plumbing | Unit 1655(a) - add two bathrooms and 1-kitchen in new ADU on ground floor. PP20240725077 | Jul 25, 2024 → Nov 7, 2025 | — | |
| Plumbing | Work category: 4pa; install a new fire sprinkler system per nfpa 13, including 2-inch fire service, total 26 heads. , ref#2025-0113-8173. PW20250115352 | Jan 15, 2025 → Jun 23, 2025 | — |
1 other permit on this lot during the project, not counted
| Other | Re-roofing: remove and replace roofing material / existing roofing material (in-kind). 202501208651 · American Standard Roofing INC | filed Jan 2025 · issued Jan 2025 · done Jan 2025 | $15k | city record |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 5342, lot 012
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.