Converted · ground-floor conversion · Lone Mountain/USF
1667A Fulton St
Completed Mar 2026+1 unit on this lot · now 35 permits
Addition of 1 new ADU. New foundation & lowered ground floor to provide head clearance for the new units. Properties have no street frontage.
filed Dec 2022issued Aug 2024 · permit wait 1 year 8 monthscompleted Mar 2026 · built in 1 year 7 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$212,340
declared across 2 permits: the ADU permit plus its sub-permits
Permit wait
1 year 8 months
filed → issued
Build time
1 year 7 months
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Addition of 1 new ADU. New foundation & lowered ground floor to provide head clearance for the new units. Properties have no street frontage. 202212138159 · Rua Woods Construction INC | filed Dec 2022 · issued Aug 2024 · done Mar 2026 | $212k | city record |
| Revision | Obtain revision to pa#: 202212138159. Revision to reflect as built conditions in kitchen and front yard. Add gate for ramp, move stove, garbage under stairs. Inspector's request. 202602276686 · cites 202212138159 · Rua Woods Construction INC | filed Feb 2026 · issued Mar 2026 · done Mar 2026 | $800 | city record |
| Plumbing | Add floor drain & sump pumb at rear yard installation to pw20241205561. PP20250115005 | Jan 15, 2025 | — | |
| Plumbing | Work category: 1p; add floor drain & sump pump installation at rear yard to pw20241205561. PW20250219180 | Feb 19, 2025 → Feb 21, 2025 | — | |
| Plumbing | Work category: 1p; to obtain a final inspection for work approved under previous permit #pw20241205561. PW20260119977 | Jan 19, 2026 → Jan 26, 2026 | — |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 1185, lot 051
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.