Converted · ground-floor conversion · Oceanview/Merced/Ingleside
174 Farallones St
In progress+1 unit on this lot · now 25 permits
Relocate existing kitchen at second floor, construct new bedroom at second floor, construct ADU at ground floor form prior approved floor plans, construct new deck at rear of house.
filed Jan 2026issued May 2026 · permit wait 4 months5 months since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$149,326 + other work
the permit also covers work unrelated to the ADU, so this is not an ADU price
Permit wait
4 months
filed → issued
Build time
in progress
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Relocate existing kitchen at second floor, construct new bedroom at second floor, construct ADU at ground floor form prior approved floor plans, construct new deck at rear of house. 202512242634 · Sunny Ca International INC | filed Jan 2026 · issued May 2026 | $149k | city record |
| Electrical | Addition of lights in the kitchen and bedrooms in the upstairs unit. EW202606245872 | Jun 24, 2026 → Jul 29, 2026 | — | |
| Electrical | Permit to legalize kitchen in unit for previous work performed. Reference permit #202512242634. EW202608157192 | Aug 15, 2026 | — | |
| Plumbing | Work category: 1p; new kitchen sink plumbing. PW20260624937 | Jun 24, 2026 → Aug 7, 2026 | — | |
| Plumbing | Work category: 1p; permit to legalize plumbing in kitchen for work previously performed. Reference building permit 202512242634. PW20260815281 | Aug 15, 2026 | — |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 7104, lot 019
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.