Converted · ground-floor conversion · Sunset/Parkside

1746 36th Ave

Completed Nov 2023+1 unit on this lot · now 27 permits

Addition of one ADU unit at the first floor per the local ADU program. The project also proposes to enlarge the sliding doors in the rear bedrooms at the second floor.

filed Apr 2022issued Sep 2022 · permit wait 5 monthscompleted Nov 2023 · built in 1 year 2 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$103,847 + other work
the permit also covers work unrelated to the ADU, so this is not an ADU price
Permit wait
5 months
filed → issued
Build time
1 year 2 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitAddition of one ADU unit at the first floor per the local ADU program. The project also proposes to enlarge the sliding doors in the rear bedrooms at the second floor.
202204222760 · H D Construction Company
filed Apr 2022 · issued Sep 2022 · done Nov 2023$80kcity record
SprinklersInstallation of new sprinkler system at entire g/f according to permit 202204222760 per nfpa 13 (2022). 17 total heads. Includes dedicated 2" underground piping per nfpa 24 (trench, backfill at sidewalk repair by separate permit). Sprinkler monitoring under separate permit.
202301049659 · cites 202204222760 · Project Contractor INC
filed Jan 2023 · issued Jan 2023 · done Oct 2023$20kcity record
SprinklersIntall new sprinkler monitoring system.
202305167806 · Crime Watch Security Sys Llc
filed May 2023 · issued May 2023 · done Oct 2023$4,000city record
ElectricalReplace service panel for 1746/1746a 36th ave. 200a incoming. 1-125a, 1 100a service panel.
E202211103541
Nov 10, 2022 → Jul 14, 2023—
ElectricalInstallation of a sprinkler monitoring system.
EW202306121776
Jun 12, 2023 → Jun 20, 2023—
PlumbingAdd 1 kitchen for 1746a 36th ave for ADU.
PP20221110084
Nov 10, 2022 → Jun 8, 2023—
PlumbingWork category: 4pa; installation of new sprinkler system at entire ground floor according to fire sprinkler permit # 202301049659 and also refer to building permit # 202204222760 per nfpa 13 2022. Total: 17 fire sprinkler heads. Includes dedicated 2" underground piping per nfpa 24 (trench, backfill and sidewalk repair by separate permit).
PW20230117035
Jan 17, 2023 → May 31, 2023—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 2014, lot 005C
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map