Converted · ground-floor conversion · Inner Richmond

175 5th Ave

In progress+1 unit on this lot · now 36 permits

Floor 1: add ADU per state law. Add 1 bedroom, kitchen, great room and 2 full baths.

filed May 2023issued Mar 2024 · permit wait 10 months2 years 7 months since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$202,610
declared across 2 permits: the ADU permit plus its sub-permits
Permit wait
10 months
filed → issued
Build time
in progress
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitFloor 1: add ADU per state law. Add 1 bedroom, kitchen, great room and 2 full baths.
202304065251 · Sky River Builder INC
filed May 2023 · issued Mar 2024$185kcity record
SprinklersInstallation of (14) fire sprinkler heads throughout ground flr according to pa# 202304065251 per nfpa 13r 2022 + underground piping per nfpa 24 (trech, backfill & sidewalk repair by other under separate permit.
202505297519 · cites 202304065251 · Project Contractor INC
filed May 2025 · issued May 2025$18kcity record
Electrical175-175 5th ave add 1 new ADU, new lights & outlets.
E202410087357
Oct 8, 2024—
ElectricalInatall ADU.
EW202606035355
Jun 3, 2026 → Jun 22, 2026—
PlumbingWork category: 2pa; install a du.
PW20260603388
Jun 3, 2026 → Jun 25, 2026—
PlumbingWork category: 4pa; renewal of expired plumbing permit# pw20250603684. Installation of (14) fire sprinkler heads throughout ground floor according to fire sprinkler permit app#2025 0529 7519, also refers to building permit app#2023 0406 5251 per nfpa 13r 2022 & underground piping per nfpa 24 (trench, backfill and sidewalk repair by other under separate permit.
PW20260716532
Jul 16, 2026 → Jul 29, 2026—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 1365, lot 010
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map