Converted · ground-floor conversion · Pacific Heights
1756 Broadway
Completed Dec 2025+1 unit on this lot · now 87 permits
Convert existing undocumented ground floor unit to become studio 1 bath ADU. Reference soft story work under separate permit #202210144345.
filed Apr 2023issued Apr 2024 · permit wait 1 yearcompleted Dec 2025 · built in 1 year 8 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$209,942
declared across 3 permits: the ADU permit plus its sub-permits
Permit wait
1 year
filed → issued
Build time
1 year 8 months
issued → completed
Builder
Pattani Construction CompanyAlso on this project: J C P Fire Protection INC, K K Electric & Alarm Company
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Convert existing undocumented ground floor unit to become studio 1 bath ADU. Reference soft story work under separate permit #202210144345. 202304266459 · Pattani Construction Company | filed Apr 2023 · issued Apr 2024 · done Dec 2025 | $150k | city record |
| Sprinklers | Install a new nfpa 13 fire sprinkler system through an new ADU and the 1st flr. Within the main building and 2" dedicate fire service. Undergournd per nfpa24 underground copper tpe k. Ref permit 202301200516. 202409201233 · J C P Fire Protection INC | filed Sep 2024 · issued Sep 2024 · done Sep 2025 | $30k | city record |
| Related permit | Upgrade existing fire alarm system per ord 165-16 sec 1103. 7. 6. 1 2016 sffc with new fire alarm system. Ref#202409201233. 202505086100 · K K Electric & Alarm Company | filed May 2025 · issued May 2025 · done Sep 2025 | $30k | city record |
| Electrical | Install 1 bathroom fan, 1 garbage disposal, 18 outlets, 11 recessed lights and 7 switches. 1 d/w, 1 range, 1 s/d. 2211 recetpacles. E202407235770 | Jul 23, 2024 → Oct 10, 2025 | — | |
| Electrical | Upgrade existing fire alarm system with a new fire alarm system. E202505092330 | May 9, 2025 → Sep 22, 2025 | — | |
| Plumbing | Install 1 tub, 1 toilet, 1 kitchen sink, 1 bathroom sink. PP20240723013 | Jul 23, 2024 → Nov 14, 2025 | — | |
| Plumbing | Work category: 4pa; install a new nfpa13 fire sprinkler system through a new ADU in an existing garage detached and onto the first floor within the main building and a 2" dedicated fire service underground copper type k underground piping copper type k. PW20240923776 | Sep 23, 2024 → Sep 15, 2025 | — |
3 other permits on this lot during the project, not counted
| Other | Revision to permit 202210144345. Voluntary foundation reinforcement of crawl space. (front building). 202504214833 · Pattani Construction Company | filed Apr 2025 · issued Jul 2025 · done Dec 2025 | $30k | city record |
| Other | To obtain final inspection for work approved under pa 202405152192. All work is complete. 202512010607 · Pattani Construction Company | filed Dec 2025 · issued Dec 2025 · done Dec 2025 | — | city record |
| Other | To obtain final inspection for work approved under pa 202302141986. All work is complete. 202512010608 · Pattani Construction Company | filed Dec 2025 · issued Dec 2025 · done Dec 2025 | — | city record |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 0569, lot 009
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.