Converted · garage conversion · Sunset/Parkside
1782A 39th Ave
In progress+1 unit on this lot · now 39 permits
Convert ground floor garage / storage into acessory dwelling unit (a. D. U. )build a two-bedroom, two-bathroom. Build an exit passageway from the rear yard to the front yard. Install new tankless water heater & mini package units. No new work on the second and third floors. (2 units + ADU).
filed Nov 2023issued Aug 2024 · permit wait 9 months2 years 3 months since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$326,446
declared across 4 permits: the ADU permit plus its sub-permits
Permit wait
9 months
filed → issued
Build time
in progress
issued → completed
Builder
Fortress Construction INCAlso on this project: Wd Fire Protection INC, Crime Watch Security Sys Llc
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Convert ground floor garage / storage into acessory dwelling unit (a. D. U. )build a two-bedroom, two-bathroom. Build an exit passageway from the rear yard to the front yard. Install new tankless water heater & mini package units. No new work on the second and third floors. (2 units + ADU). 202311030160 · Fortress Construction INC | filed Nov 2023 · issued Aug 2024 | $285k | city record |
| Revision | Revision to 202311030160. New foundation and bearing wall to replace existing post and beam at rear. 202409181075 · cites 202311030160 · Fortress Construction INC | filed Sep 2024 · issued Sep 2024 | $8,000 | city record |
| Sprinklers | Install new fire sprinklers systems per nfpa 13r throughout ground floor and corridor egress including 2" dedicated fire service per nfpa24 ref pa 202311030160. 202410112805 · cites 202311030160 · Wd Fire Protection INC | filed Oct 2024 · issued Oct 2024 · done Mar 2026 | $23k | city record |
| Sprinklers | Installation of a new sprinkler monitoring system. 202503061713 · Crime Watch Security Sys Llc | filed Mar 2025 · issued Mar 2025 · done Mar 2026 | $10k | city record |
| Electrical | New lights at a new kitchen, 2 bathroom, dining room, living room, and 2 bedroom. E202408066064 | Aug 6, 2024 → Mar 16, 2026 | — | |
| Electrical | Online electrical permit: 60 of buildings of 6 dwelling units or less. Installation of a sprinkler monitoring system. E202603069453 | Mar 6, 2026 → Mar 17, 2026 | — | |
| Electrical | Ref: witness test fee for e202603069453. EW202603063303 | Mar 6, 2026 → Mar 17, 2026 | — | |
| Plumbing | Work category: 4pa; installation of a new nfpa-13r fire sprinkler system at the ADU of the property with 20 fire sprinkler heads. PW20250217114 | Feb 17, 2025 → Nov 4, 2025 | — | |
| Plumbing | To amend pp20240806263: unit a - relocate (3) gas line meter. PP20250625071 | Jun 25, 2025 → Nov 4, 2025 | — |
1 other permit on this lot during the project, not counted
| Other | Replace 6 windows on the right side( same size, same locations, max u-factor 0. 30) and install 80 sq ft of stucco. Paint all of right side wall. 202508122876 · Fortress Construction INC | filed Aug 2025 · issued Aug 2025 | $35k | city record |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 2011, lot 007A
- Why we call it an ADU