Converted · garage conversion · Sunset/Parkside

1803 Judah St

Completed May 2023+1 unit on this lot · now 68 permits

Convert e garage into a new studio ADU no 162-16.

filed Jul 2019issued Nov 2021 · permit wait 2 years 4 monthscompleted May 2023 · built in 1 year 6 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$41,638
declared across 2 permits: the ADU permit plus its sub-permits
Permit wait
2 years 4 months
filed → issued
Build time
1 year 6 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitConvert e garage into a new studio ADU no 162-16.
201907085301 · Home C Construction INC
filed Jul 2019 · issued Nov 2021 · done May 2023$40kcity record
SprinklersFire sprinkler t. I at new ADU & egress, relocate 1 & add 2 sprinklers. Ref pa# 201907085301.
202201316966 · cites 201907085301 · Pro Plumbing & Fire Sprinkler INC
filed Jan 2022 · issued Jan 2022 · done Mar 2023$1,638city record
ElectricalInstall all new electrical wire for the ADU unit.
EW202112220450
Dec 22, 2021 → Mar 28, 2023—
ElectricalAll new wiring in ADU.
E202203158945
Mar 15, 2022—
ElectricalInstall new 400 amps electrical service, 6 residential meter socket one house meter socket. .
EW202209135994
Sep 13, 2022 → Mar 28, 2023—
PlumbingWork category: 1p; replace 30 gal water heater with tankless water heater.
PW20211215328
Dec 15, 2021 → Apr 18, 2022—
PlumbingWork category: 4pa; tennant improvement in ADU unit and sprinkler riser.
PW20220201465
Feb 1, 2022 → Feb 8, 2022—
PlumbingNew plumbing for ADU.
PP20220315674
Mar 15, 2022 → Apr 4, 2023—

Trade permits show what work was done and when; the city does not record who pulled them.