Converted · garage conversion · Sunset/Parkside
1803 Judah St
Completed May 2023+1 unit on this lot · now 68 permits
Convert e garage into a new studio ADU no 162-16.
filed Jul 2019issued Nov 2021 · permit wait 2 years 4 monthscompleted May 2023 · built in 1 year 6 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$41,638
declared across 2 permits: the ADU permit plus its sub-permits
Permit wait
2 years 4 months
filed → issued
Build time
1 year 6 months
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Convert e garage into a new studio ADU no 162-16. 201907085301 · Home C Construction INC | filed Jul 2019 · issued Nov 2021 · done May 2023 | $40k | city record |
| Sprinklers | Fire sprinkler t. I at new ADU & egress, relocate 1 & add 2 sprinklers. Ref pa# 201907085301. 202201316966 · cites 201907085301 · Pro Plumbing & Fire Sprinkler INC | filed Jan 2022 · issued Jan 2022 · done Mar 2023 | $1,638 | city record |
| Electrical | Install all new electrical wire for the ADU unit. EW202112220450 | Dec 22, 2021 → Mar 28, 2023 | — | |
| Electrical | All new wiring in ADU. E202203158945 | Mar 15, 2022 | — | |
| Electrical | Install new 400 amps electrical service, 6 residential meter socket one house meter socket. . EW202209135994 | Sep 13, 2022 → Mar 28, 2023 | — | |
| Plumbing | Work category: 1p; replace 30 gal water heater with tankless water heater. PW20211215328 | Dec 15, 2021 → Apr 18, 2022 | — | |
| Plumbing | Work category: 4pa; tennant improvement in ADU unit and sprinkler riser. PW20220201465 | Feb 1, 2022 → Feb 8, 2022 | — | |
| Plumbing | New plumbing for ADU. PP20220315674 | Mar 15, 2022 → Apr 4, 2023 | — |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 1830, lot 001
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.