Converted · ground-floor conversion · Lone Mountain/USF
1851 Fulton St
In progress+1 unit on this lot · now 71 permit
Add 1 accessory dwelling unit to 1st flr per ordinance 162-16.
filed Jan 2018issued Mar 2022 · permit wait 4 years 2 months4 years 8 months since issue
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$45,000
declared on the ADU permit
Permit wait
4 years 2 months
filed → issued
Build time
in progress
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Add 1 accessory dwelling unit to 1st flr per ordinance 162-16. 201801239316 | filed Jan 2018 · issued Mar 2022 | $45k | city record |
1 other permit on this lot during the project, not counted
| Other | Recommencement and completion of work approved under pa# 201706028230, 201709259513. 202403157900 · Kelly Brother'S Construction | filed Mar 2024 · issued Mar 2024 · done May 2024 | $20k | city record |
These permits also cite 201706028230, 201709259513, which the city filed before our records begin.
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 1187, lot 009E
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.