Detached · Sunset/Parkside
191 Gellert Dr
Completed May 2026+2 units on this lot21 permits
Building b - to erect a 3-story, type 5a, a single family dwelling with one ADU per state program. (2 units total).
filed Feb 2022issued May 2023 · permit wait 1 year 3 monthscompleted May 2026 · built in 3 years
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$816,019 for 2 ADUs
one permit, 2 units; not a per-unit price
Permit wait
1 year 3 months
filed → issued
Build time
3 years
issued → completed
Builder
No contractor listed
Also on this project: Best Care Fire Protection, Poly - On Electrical, Firstpv Inc Dba Solarunion, All Bay Solar Construction INC, Electric M D
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Building b - to erect a 3-story, type 5a, a single family dwelling with one ADU per state program. (2 units total). 202202178259 | filed Feb 2022 · issued May 2023 · done May 2026 | $730k | city record |
| Sprinklers | Building a: install a new fire sprinkler system per nfpa13 throughout entire building, including 2-inch dedicated fire service total 45 heads, ref pa# 202202178257-s1. 202309196864 · Best Care Fire Protection | filed Sep 2023 · issued Sep 2023 · done Dec 2024 | $33k | city record |
| Sprinklers | Install a new fire sprinkler slystem per nfpa 13, 2022 throughout entire building including 2 inch dedicated fire service total 40 heads. Ref pa# 2022-0217-8259-s1. 202404220425 · cites 202202178259 · Best Care Fire Protection | filed Apr 2024 · issued Apr 2024 · done Dec 2024 | $29k | city record |
| Sprinklers | Install a new sprinkler monitoring system per nfpa 72-2022 section 23. 8. 5. 5. 1 with (1) fire alarm condrol unit (1) wirelss commercial fire communicator (1) smoke detector above the facu (1) manual pull station with reference sprinkler per nfpa 13 #202309196864. 202407257276 · Poly - On Electrical | filed Jul 2024 · issued Jul 2024 · done Dec 2024 | $12k | city record |
| Sprinklers | Install a new sprinkler monitoring system per nfpa 72-2022 section 23. 8. 5. 5-1 with 1- fire alarm control unit, 1-wireless commericial fire communicator, 1-smoke detector above the facu, 1 manuel pull station. Ref sprinkler per nfpa 13 #202404220425. 202407257286 · Poly - On Electrical | filed Jul 2024 · issued Jul 2024 · done Dec 2024 | $12k | city record |
| Electrical | Cei to install ufer ground at this property only. EW202307172540 | Jul 17, 2023 | — | |
| Electrical | New building: five bedroom, four bathrooms, kitchen, living and laundry. EW202311145172 | Nov 14, 2023 | — | |
| Electrical | New ADU: one bed, one bathroom, kitchen, living and laundry. EW202311145173 | Nov 14, 2023 | — | |
| Electrical | Install one 400a underground service. EW202312225857 | Dec 22, 2023 | — | |
| Electrical | New house with five bedrooms, three bathrooms, office, kitchen, living, laundry and garage. New 400a underground service. EW202404188132 | Apr 18, 2024 | — | |
| Electrical | New ADU one bedroom, kitchen, living, bathroom and laundry. EW202404188133 | Apr 18, 2024 | — | |
| Electrical | Install a new sprinkler monitoring system per nfpa 7202022 section 23. 8. 5. 5. 1 with ref pa 202309196864. E202407255856 | Jul 25, 2024 → Nov 25, 2024 | — | |
| Electrical | Install a new sprinkler monitoring system per nfpa 72 2022 section 23. 8. 5. 5. 1 with ref pa 202404220425. E202407255858 | Jul 25, 2024 → Dec 6, 2024 | — | |
| Electrical | Install ess battery (29, xkwh), inverter and one switch and chargeverter. E202411208347 | Nov 20, 2024 → Nov 25, 2024 | — | |
| Electrical | Ref 202411215444- electrical for ess battery, switch and inverter. E202411218369 | Nov 21, 2024 → Dec 20, 2024 | — | |
| Plumbing | Work category: 2pb; plumbing work; install five full bathrooms, two kitchens, two laundry, rain gutter and underground work. PW20230910009 | Sep 10, 2023 → Jul 31, 2024 | — | |
| Plumbing | Work category: 1m; install new heat pump system for unit #201 #201a install vent pipe. PMW20231217386 | Dec 17, 2023 → Jul 26, 2024 | — | |
| Plumbing | Work category: 4pa; install a new fire sprinkler system per nfpa 13 throughout the building. Including 2-inch dedicated fire service. Total 45 heads. PW20231220448 | Dec 20, 2023 → Dec 2, 2024 | — | |
| Plumbing | Work category: 2pb; plumbing work; new install four full bathrooms, two kitchen, two laundry, roof drain, floor drains and underground. PW20240318410 | Mar 18, 2024 → Sep 10, 2024 | — | |
| Plumbing | Work category: 1m; install three heat pump system for unit #191 #191a install vent pipe. PMW20240416128 | Apr 16, 2024 → Sep 17, 2024 | — | |
| Plumbing | Work category: 4pa; install a new fire sprinkler system per nfpa 13, 2022 throughout the building. Including a 2-inch fire service, a total of 40 heads. Ref# 2024-0422-0425. PW20240422244 | Apr 22, 2024 → Dec 2, 2024 | — |
6 other permits on this lot during the project, not counted
| Other | Install 10'-0" tall concrete fence along south and east side of property. 202312072063 | filed Dec 2023 · issued Dec 2023 · done Nov 2024 | $50k | city record |
| Other | Install a roof mounted pv solar system. 5. 74kw. 202406144516 · Firstpv Inc Dba Solarunion | filed Jun 2024 · issued Oct 2024 · done Feb 2025 | $28k | city record |
| Other | Install new roof mounted solar system 5. 67kw (14 panels) 405 watt modules. Ref pa# 202202178257. 202408027803 · All Bay Solar Construction INC | filed Aug 2024 · issued Sep 2024 · done Jan 2025 | $15k | city record |
| Other | Battery storage system to provide temporary power to 2 residential dwelling units until pg&e energizes the building; 29. 2 kwh; inverter (eg4 18 kpv) (rule 21, ca. Approved); 2 batteries (eg4 pro 14. 6 kwh 48 dclfp) (ul1973, ul954oa approved). 202411185166 · Electric M D | filed Nov 2024 · issued Nov 2024 · done Dec 2024 | $20k | city record |
| Other | Battery storage (1x ess)-29. 2kwh. And batteries and two units powered from same temp source. 202411215444 · Electric M D | filed Nov 2024 · issued Nov 2024 · done Jan 2025 | $20k | city record |
| Other | Revision to pa # 202408027803: installing a new roof mounted solar system 5. 67kw (14) 405 w modules. Revised application for changes made in the single line diagram. 202411145001 · All Bay Solar Construction INC | filed Dec 2024 · issued Jan 2025 · done Jan 2025 | $15k | city record |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 7260A, lot 002
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.