Converted · legalization · Inner Sunset
1926A 9th Ave
Completed Dec 2023+1 unit on this lot · now 24 permits
To comply with (nov) #202061911, #202061901, #202061101. Legalize accessory dwelling unit added on ground floor approx. 600 SF per state law and city ordinance #162-16. Two new bedrooms, new kitchen, and new walk-way to front of house & two new furnaces.
filed Nov 2020issued Oct 2022 · permit wait 1 year 11 monthscompleted Dec 2023 · built in 1 year 2 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$60,000
declared on the ADU permit
Permit wait
1 year 11 months
filed → issued
Build time
1 year 2 months
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | To comply with (nov) #202061911, #202061901, #202061101. Legalize accessory dwelling unit added on ground floor approx. 600 SF per state law and city ordinance #162-16. Two new bedrooms, new kitchen, and new walk-way to front of house & two new furnaces. 202011179111 · Be Pro Construction INC | filed Nov 2020 · issued Oct 2022 · done Dec 2023 | $60k | city record |
| Revision | Revision to pa202011179111 to include added language for a new stair at rear of building. 202308043829 · Be Pro Construction INC | filed Aug 2023 · issued Aug 2023 · done Dec 2023 | — | city record |
| Electrical | Legalize ADU at ground floor. New kitchen gfci recep. E202308238903 | Aug 23, 2023 → Dec 1, 2023 | — | |
| Plumbing | Legalize ADU at ground floor. New kitchen sink. PP20230823616 | Aug 23, 2023 → Oct 18, 2023 | — |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 2126, lot 015B
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.