New dwelling unit (ADU) (195 eureka st. )per government code section 66314, state ADU law. At basement floor. Modify existing storage space and garage space for 1 new ADU. New unit to include bathroom, bedroom & kitchen. Maher n/a.

filed Jun 2020issued Oct 2024 · permit wait 4 years 4 monthscompleted Sep 2026 · built in 1 year 11 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$197,258
declared across 2 permits: the ADU permit plus its sub-permits
Permit wait
4 years 4 months
filed → issued
Build time
1 year 11 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitNew dwelling unit (ADU) (195 eureka st. )per government code section 66314, state ADU law. At basement floor. Modify existing storage space and garage space for 1 new ADU. New unit to include bathroom, bedroom & kitchen. Maher n/a.
202006299335 · Allied Teamwork Construction INC
filed Jun 2020 · issued Oct 2024 · done Sep 2026$181kcity record
SprinklersInstall new fire sprinklers per nfda-13-r throughout new ADU inclusion 2" dedicated fire service. Ref pa #202006299335.
202506057966 · cites 202006299335 · All Star Fire Protection LLC
filed Jun 2025 · issued Jun 2025 · done Jun 2026$16kcity record
RevisionRevision to pa 202006299335 to reflect correct existing garage size it takes up full width of lot and adjust floor plan per plans.
202510217820 · cites 202006299335 · Allied Teamwork Construction INC
filed Oct 2025 · issued Oct 2025 · done Sep 2026—city record
RevisionRevision to pa# 202510217820 & 202006299335: provide wood step next to bedroom window, comply with eero.
202608317483 · cites 202006299335 · Allied Teamwork Construction INC
filed Aug 2026 · issued Aug 2026 · done Sep 2026—city record
ElectricalConnect kitchen, bathroom, laundry and bedroom for ADU.
E202511207275
Nov 20, 2025 → May 13, 2026—
ElectricalOnline electrical permit: 4 of 4 - 9 floors. Install a new dedicated fa system (sprinkler monitoring) per nfpa 72-2025 section 23. 8. 5. 5. 1 with: (1) fire alarm control unit (1) wireless commercial fire communicator (1) smoke detector above the facu (1) manual pull.
E202605181031
May 18, 2026—
ElectricalOnline electrical permit: 60 of buildings of 6 dwelling units or less. Install a new dedicated fa system (sprinkler monitoring) per nfpa 72-2025 section 23. 8. 5. 5. 1 with: (1) fire alarm control unit (1) wireless commercial fire communicator (1) smoke detector above.
E202605181033
May 18, 2026—
ElectricalOnline electrical permit: category 4a: installation of fire warning and controlled devices of up to 2, 500 ft². 1. Install a new dedicated fa system (sprinkler monitoring) per nfpa 72-2025 section 23. 8. 5. 5. 1 with: (1) fire alarm control unit (1) wireless commercial.
E202605191040
May 19, 2026 → Jun 3, 2026—
PlumbingInstall new fire sprinklers per nfda-13-r throughout new ADU inclusion 2" dedicated fire service. Ref pa #202006299335.
PP20250605687
Jun 5, 2025 → Jun 3, 2026—
PlumbingConnect heating system for ADU.
PM20251120963
Nov 20, 2025 → May 11, 2026—
PlumbingConnect kitchen, bathroom and laundry at ADU.
PP20251120964
Nov 20, 2025 → May 11, 2026—

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 2693, lot 021
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house