Converted · garage conversion · Outer Mission
1965 San Jose Ave
Completed Feb 2024+1 unit on this lot · now 25 permits
Adding ADU at the ground floor per ordinance 162-16, garage infill.
filed Dec 2019issued Apr 2022 · permit wait 2 years 4 monthscompleted Feb 2024 · built in 1 year 11 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$100,244
declared across 2 permits: the ADU permit plus its sub-permits
Permit wait
2 years 4 months
filed → issued
Build time
1 year 11 months
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | Adding ADU at the ground floor per ordinance 162-16, garage infill. 201912058797 · Hang C Construction INC | filed Dec 2019 · issued Apr 2022 · done Feb 2024 | $100k | city record |
| Related permit | Per pa #201912058797, add addres to ADU at apn 3212/042 as 1965a san jose ave. M1230547 · cites 201912058797 | filed Apr 2023 · issued Apr 2023 | $244 | city record |
| Electrical | New remodel on 2/f and new uint on 1/f, 2/f electrical upgrade, add new kitchen and rooms, two bathrooms on 1/f upgrade of new service and add a new 100 amp meter. 100a service, 24 circuits, 50 lights, 24 switches, 50 receptaces, 6 fans, 2 g/d, 2 range, 10 smoke detectors. E20220531473 | May 31, 2022 → Jul 3, 2023 | — | |
| Plumbing | Replace a 70. 000 btu furnace on 2/f, install a new 70000 btu furnace on 1/f, install a new chimney to roof. PM20220531148 | May 31, 2022 → Jul 20, 2023 | — | |
| Plumbing | Two bathroom and kitchen remodel on 2/f, two new bathroom and a knew kitchen on 1/f, two laundry rooms. PP20220531147 | May 31, 2022 → Jul 20, 2023 | — |
Trade permits show what work was done and when; the city does not record who pulled them.
- Lot
- block 3212, lot 042
- Why we call it an ADU
- SF DBI flagged the permit as an ADU.