ADU conversion per state program for lower unit. Interior remodel 1/f (unit 200a) kitchen, bathrm, bedrm 1 & laundry rm, replace associated rough mep updates as appropriate, demo non structural sub-ceiling btw 1/f & 2/f in order to raise ceilings of lower unit. . .
filed Sep 2023issued Mar 2024 · permit wait 6 monthscompleted Nov 2024 · built in 8 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$292,369
declared on the ADU permit
Permit wait
6 months
filed → issued
Build time
8 months
issued → completed
Permits in this project
| Permit | What | When | Declared | |
|---|---|---|---|---|
| ADU permit | ADU conversion per state program for lower unit. Interior remodel 1/f (unit 200a) kitchen, bathrm, bedrm 1 & laundry rm, replace associated rough mep updates as appropriate, demo non structural sub-ceiling btw 1/f & 2/f in order to raise ceilings of lower unit. . . 202309297692 · Pristine Building Companies INC | filed Sep 2023 · issued Mar 2024 · done Nov 2024 | $292k | city record |
| Electrical | Upgrading existing (2) main service panels from 100-200 amps & complete rewire of unit 200 ft. With addition outlets, switch per plan. (20) lights, (10) switches, (20) receptacles, (1) fan, (1) dishwasher, (1) garbage disposal, (1) microwave, (1) ranges, (4) smoke detectors. E202404013451 | Apr 1, 2024 → Nov 1, 2024 | — | |
| Electrical | Electrical permit for a garage project was filed by another contractor. Contractor never finaled the work done to garage space. This permit is an attempt to finalize the work performed. Rough inspection was signed off by matthew schlect on 4/22/2022 under permit #202204209727. EW202405048492 | May 4, 2024 → May 13, 2024 | — | |
| Plumbing | Installation of hvac unit for unit 200a. PM20240401116 | Apr 1, 2024 → Nov 7, 2024 | — | |
| Plumbing | New rough in plumbing for bathroom. Kitchen & laundry room remodel. PP20240401117 | Apr 1, 2024 → Nov 7, 2024 | — | |
| Plumbing | Unit 200a -ref: pp20240401116- to include underground plumbing line work. PP20240501612 | May 1, 2024 → Nov 7, 2024 | — | |
| Plumbing | Work category: 1p; extending houseline gas plumbing to facilitate meter move. PW20241118216 | Nov 18, 2024 → Dec 4, 2024 | — |
1 other permit on this lot during the project, not counted
| Other | Replace existing sleepered crawl space with new framed crawl space. Add new continous foundation along center line of building. Revision to pa 202309297632. Replace interior partition walls in kind. 202405011134 · Pristine Building Companies INC | filed May 2024 · issued May 2024 · done Nov 2024 | $20k | city record |
These permits also cite 202309297632, which the city filed before our records begin.