Converted · ground-floor conversion · Bernal Heights

200 Ellsworth St

Completed Nov 2024+1 unit on this lot · now 27 permits

ADU conversion per state program for lower unit. Interior remodel 1/f (unit 200a) kitchen, bathrm, bedrm 1 & laundry rm, replace associated rough mep updates as appropriate, demo non structural sub-ceiling btw 1/f & 2/f in order to raise ceilings of lower unit. . .

filed Sep 2023issued Mar 2024 · permit wait 6 monthscompleted Nov 2024 · built in 8 months
waiting for permitconstructionrelated building permitelectrical permitplumbing permit
Declared value
$292,369
declared on the ADU permit
Permit wait
6 months
filed → issued
Build time
8 months
issued → completed

Permits in this project

PermitWhatWhenDeclared
ADU permitADU conversion per state program for lower unit. Interior remodel 1/f (unit 200a) kitchen, bathrm, bedrm 1 & laundry rm, replace associated rough mep updates as appropriate, demo non structural sub-ceiling btw 1/f & 2/f in order to raise ceilings of lower unit. . .
202309297692 · Pristine Building Companies INC
filed Sep 2023 · issued Mar 2024 · done Nov 2024$292kcity record
ElectricalUpgrading existing (2) main service panels from 100-200 amps & complete rewire of unit 200 ft. With addition outlets, switch per plan. (20) lights, (10) switches, (20) receptacles, (1) fan, (1) dishwasher, (1) garbage disposal, (1) microwave, (1) ranges, (4) smoke detectors.
E202404013451
Apr 1, 2024 → Nov 1, 2024—
ElectricalElectrical permit for a garage project was filed by another contractor. Contractor never finaled the work done to garage space. This permit is an attempt to finalize the work performed. Rough inspection was signed off by matthew schlect on 4/22/2022 under permit #202204209727.
EW202405048492
May 4, 2024 → May 13, 2024—
PlumbingInstallation of hvac unit for unit 200a.
PM20240401116
Apr 1, 2024 → Nov 7, 2024—
PlumbingNew rough in plumbing for bathroom. Kitchen & laundry room remodel.
PP20240401117
Apr 1, 2024 → Nov 7, 2024—
PlumbingUnit 200a -ref: pp20240401116- to include underground plumbing line work.
PP20240501612
May 1, 2024 → Nov 7, 2024—
PlumbingWork category: 1p; extending houseline gas plumbing to facilitate meter move.
PW20241118216
Nov 18, 2024 → Dec 4, 2024—
1 other permit on this lot during the project, not counted
OtherReplace existing sleepered crawl space with new framed crawl space. Add new continous foundation along center line of building. Revision to pa 202309297632. Replace interior partition walls in kind.
202405011134 · Pristine Building Companies INC
filed May 2024 · issued May 2024 · done Nov 2024$20kcity record

These permits also cite 202309297632, which the city filed before our records begin.

Trade permits show what work was done and when; the city does not record who pulled them.

Lot
block 5662, lot 001
Why we call it an ADU
SF DBI flagged the permit as an ADU.
Claim this project or house

City record of the ADU permitProperty Information Map